Construction progress for September 2023
14.09.2023
Metropolis by DIM is being built at a fast pace!
We share the latest news from the site for September:
Building No. 3, Section 1:
placement of NVF - 94%;
arrangement of SPOK - 90%;
arrangement of the roof - 99%;
installation of elevator equipment - 33%;
sewerage installation K1 room-4,200 - 85%;
laying of low-current fire networks of the MZK - 10%.
Building No. 3, Section 2:
arrangement of the NVF - 99%;
arrangement of SPOK - 98%;
arrangement of the roof - 98%;
arrangement of LMM of the building - 80%;
installation of elevator equipment - 40%;
installation of pipeline B1.2 – 75%;
plastering of the walls of the MZK - 100%;
laying electrical networks (horizontal) for lighting MZK - 20%.
Building No. 3, Section 3:
installation of a cement-sand screed floor - 99%;
arrangement of the NVF - 98%;
arrangement of SPOK - 99%;
laying tiles on the floor in the MZK - 85%;
installation of the fire protection system of the MZK, apartments - 25%;
installation of elevator equipment - 40%;
installation of metal entrance doors to the apartment - 95%.
Railway station parking lot No. 3:
arrangement of the ventilation system B-1-2-3-4-5-6-7-8, P-1 – 93%;
decoration of the MZK of the basement residential part - 90%;
installation of engineering equipment in technical premises - 30%;
installation of main lines B1.2-B2.2 – 50%;
installation of smoke removal ducts – 15%.
Building No. 4, Section 1:
Arrangement of s/b structures:
reinforcement and concreting of vertical and horizontal elements of the building of the 19th floor - 100%;
arrangement of internal and external brick walls - 30%;
installation of staircases on the 15th and 16th floors - 20%;
installation of ventilation units - 40%.
Building No. 4, Section 2:
implementation of monolithic parking works.
Building No. 4, Section 3:
Arrangement of s/b structures:
reinforcement and concreting of vertical elements of the building on the 9th floor - 100%;
installation of ventilation units - 15%;
installation of staircases - 4%.