Metropolis by DIM is being built at a fast pace!

We share the latest news from the site for September:

Building No. 3, Section 1:

  • placement of NVF - 94%;

  • arrangement of SPOK - 90%;

  • arrangement of the roof - 99%;

  • installation of elevator equipment - 33%;

  • sewerage installation K1 room-4,200 - 85%;

  • laying of low-current fire networks of the MZK - 10%.

Building No. 3, Section 2:

  • arrangement of the NVF - 99%;

  • arrangement of SPOK - 98%;

  • arrangement of the roof - 98%;

  • arrangement of LMM of the building - 80%;

  • installation of elevator equipment - 40%;

  • installation of pipeline B1.2 – 75%;

  • plastering of the walls of the MZK - 100%;

  • laying electrical networks (horizontal) for lighting MZK - 20%.

Building No. 3, Section 3:

  • installation of a cement-sand screed floor - 99%;

  • arrangement of the NVF - 98%;

  • arrangement of SPOK - 99%;

  • laying tiles on the floor in the MZK - 85%;

  • installation of the fire protection system of the MZK, apartments - 25%;

  • installation of elevator equipment - 40%;

  • installation of metal entrance doors to the apartment - 95%.

Railway station parking lot No. 3:

  • arrangement of the ventilation system B-1-2-3-4-5-6-7-8, P-1 – 93%;

  • decoration of the MZK of the basement residential part - 90%;

  • installation of engineering equipment in technical premises - 30%;

  • installation of main lines B1.2-B2.2 – 50%;

  • installation of smoke removal ducts – 15%.

Building No. 4, Section 1:

Arrangement of s/b structures:

  • reinforcement and concreting of vertical and horizontal elements of the building of the 19th floor - 100%;

  • arrangement of internal and external brick walls - 30%;

  • installation of staircases on the 15th and 16th floors - 20%;

  • installation of ventilation units - 40%.

Building No. 4, Section 2:

  • implementation of monolithic parking works.

Building No. 4, Section 3:

Arrangement of s/b structures:

  • reinforcement and concreting of vertical elements of the building on the 9th floor - 100%;

  • installation of ventilation units - 15%;

  • installation of staircases - 4%.