Construction progress for November 2023
23.11.2023
Metropolis by DIM is being built at a fast pace!
We share the latest news from the site for November:
Building No. 3, Section 1:
laying electrical networks (horizontal) for lighting MZK - 70%;
placement of NVF - 97%;
arrangement of SPOK - 94%;
installation of elevator equipment - 70%;
laying of low-current fire networks of MZK - 55%;
decoration (plaster) of the walls of the MZK - 100%;
installation of entrance apartment doors - 35%.
Building No. 3, Section 2:
arrangement of LMM of the building - 82%;
installation of elevator equipment - 60%;
installation of pipeline B1.2 – 95%;
laying electrical networks (horizontal) for lighting MZK - 95%;
laying of low-current fire networks of MZK - 55%;
installation of entrance apartment doors - 100%.
Building No. 3, Section 3:
arrangement of LMM - 80%;
laying tiles on the floor in MZK - 96%
installation of the fire protection system of the MZK, apartments - 65%;
installation of elevator equipment - 100%;
installation of metal entrance doors in the apartment - 100%.
Railway station parking lot No. 3:
arrangement of the ventilation system B-1-2-3-4-5-6-7-8, P-1 – 96%;
decoration of the MZK of the basement residential part - 99%;
installation of engineering equipment in technical premises - 50%;
installation of main lines B1.2-B2.2 – 80%;
installation of smoke removal ducts - 45%;
installation of the fire water supply system - 40%.
Building No. 4, Section 1:
Arrangement of s/b structures:
reinforcement and concreting of vertical and horizontal elements of the building of the 20th floor - 33%;
arrangement of internal and external brick walls - 42%;
installation of staircases - 30%;
installation of ventilation units - 48%.
Building No. 4, Section 3:
Arrangement of s/b structures:
reinforcement and concreting of horizontal elements of the building of the 11th floor - 100%;
reinforcement and concreting of vertical elements of the 12th floor building - 40%;
installation of ventilation units - 28%;
installation of staircases - 15%.
Parking lot ШБ #4, 2nd line, 2nd starting point
reinforcement and concreting of horizontal and vertical structures - 40%.
Freestanding 3rd parking lot
reinforcement and concreting of horizontal and vertical structures - 100%.