Metropolis by DIM is being built at a fast pace!

We share the latest news from the site for November:

Building No. 3, Section 1:

  • laying electrical networks (horizontal) for lighting MZK - 70%;

  • placement of NVF - 97%;

  • arrangement of SPOK - 94%;

  • installation of elevator equipment - 70%;

  • laying of low-current fire networks of MZK - 55%;

  • decoration (plaster) of the walls of the MZK - 100%;

  • installation of entrance apartment doors - 35%.

Building No. 3, Section 2:

  • arrangement of LMM of the building - 82%;

  • installation of elevator equipment - 60%;

  • installation of pipeline B1.2 – 95%;

  • laying electrical networks (horizontal) for lighting MZK - 95%;

  • laying of low-current fire networks of MZK - 55%;

  • installation of entrance apartment doors - 100%.

Building No. 3, Section 3:

  • arrangement of LMM - 80%;

  • laying tiles on the floor in MZK - 96%

  • installation of the fire protection system of the MZK, apartments - 65%;

  • installation of elevator equipment - 100%;

  • installation of metal entrance doors in the apartment - 100%.

Railway station parking lot No. 3:

  • arrangement of the ventilation system B-1-2-3-4-5-6-7-8, P-1 – 96%;

  • decoration of the MZK of the basement residential part - 99%;

  • installation of engineering equipment in technical premises - 50%;

  • installation of main lines B1.2-B2.2 – 80%;

  • installation of smoke removal ducts - 45%;

  • installation of the fire water supply system - 40%.

Building No. 4, Section 1:

Arrangement of s/b structures:

  • reinforcement and concreting of vertical and horizontal elements of the building of the 20th floor - 33%;

  • arrangement of internal and external brick walls - 42%;

  • installation of staircases - 30%;

  • installation of ventilation units - 48%.

Building No. 4, Section 3:

Arrangement of s/b structures:

  • reinforcement and concreting of horizontal elements of the building of the 11th floor - 100%;

  • reinforcement and concreting of vertical elements of the 12th floor building - 40%;

  • installation of ventilation units - 28%;

  • installation of staircases - 15%.

Parking lot ШБ #4, 2nd line, 2nd starting point

  • reinforcement and concreting of horizontal and vertical structures - 40%.

Freestanding 3rd parking lot

  • reinforcement and concreting of horizontal and vertical structures - 100%.