Construction progress for December 2023
13.12.2023
Metropolis by DIM is being built at a fast pace!
We share the latest news from the construction site for December:
Building No. 3, Section 1:
laying electrical networks (horizontal) for lighting MZK - 80%;
arrangement of the NVF - 98%;
arrangement of SPOK - 95%;
installation of elevator equipment - 75%;
laying of low-current fire networks of MZK - 85%;
installation of entrance apartment doors - 40%.
Building No. 3, Section 2:
arrangement of LMM of the building - 85%;
installation of elevator equipment - 65%;
installation of pipeline B1.2 – 100%;
laying electrical networks (horizontal) for lighting MZK - 98%;
laying of low-current fire networks of the MZK - 85%.
Building No. 3, Section 3:
arrangement of LMM - 85%;
laying tiles on the floor in the MZK - 97%;
installation of the fire protection system of MZK, apartments - 75%.
Railway station parking lot No. 3:
arrangement of the ventilation system B-1-2-3-4-5-6-7-8, P-1 - 100%;
installation of engineering equipment in technical premises - 60%;
installation of main lines B1.2-B2.2 – 85%;
installation of smoke removal ducts - 50%;
installation of the fire water supply system - 65%.
Building No. 4, Section 1:
Arrangement of s/b structures:
reinforcement and concreting of vertical and horizontal elements of the 20th floor building - 100%;
arrangement of internal and external brick walls - 45%;
installation of staircases - 35%;
installation of ventilation units - 49%.
Building No. 4, Section 3:
Arrangement of s/b structures:
reinforcement and concreting of horizontal elements of the 12th floor building - 100%;
reinforcement and concreting of vertical elements of the 12th floor building - 50%;
installation of ventilation units - 29%;
installation of staircases - 20%.
Railway station #4 parking lot, 2nd line, 2nd start:
reinforcement and concreting of horizontal and vertical structures - 45%.