Construction progress for August 2023
24.08.2023
Metropolis by DIM is under construction! Work is in full swing on buildings 3 and 4.
We share the latest news from the construction site for August:
Building No. 3, Section 1:
arrangement of SPOK - 60%;
installation of elevator equipment - 32%;
sewage installation K1 dept. 4,200 - 80%.
Building No. 3, Section 2:
arrangement of the NVF - 98%;
arrangement of SPOK - 97%;
arrangement of the roof - 97%;
arrangement of LMM of the building - 79%;
pipeline installation B1.2.
Building No. 3, Section 3:
LMM facilities - 78%;
laying tiles on the floor in the MZK - 75%;
installation of elevator equipment - 30%;
installation of metal entrance doors to the apartment - 90%.
Railway station parking lot No. 3:
arrangement of the ventilation system B-1-2-3-4-5-6-7-8, P-1 – 91%;
decoration of the MZK of the basement residential part - 50%;
installation of engineering equipment in technical premises - 10%;
installation of main lines B1.2-B2.2 – 40%.
Building No. 4, Section 1:
Arrangement of s/b structures:
reinforcement and concreting of vertical and horizontal elements of the building on the 17th and 18th floors - 99%
arrangement of internal and external brick walls - 25%
installation of staircases on the 15th and 16th floors - 10%
installation of ventilation units - 30%
Building No. 4, Section 2:
execution of monolithic works of the parking lot, filling of the wall of the parking lot, which is connected with section 2 of the building. #4;
execution of the monolith of the power plate to the stylobate part.
Building No. 4, Section 3:
Arrangement of s/b structures:
installation of ventilation units - 9%;
installation of staircases - 3%.