Construction progress for January 2023
19.01.2023
After the New Year holidays, the modern and stylish METROPOLIS with renewed strength and tenacity began the construction of all stages of the complex at once. We report what was done on the construction site in January 2023. Building No. 3, section 1: Installation of internal brick walls from the 3rd to 34th floor - 98% Completed work on laying heating pipelines for apartments - 98% Installation of cement-sand screed floor - 80% Laying of electrical networks (horizontal) for powering apartments and boilers, MZK – 85% Arrangement of NVF – 80% Arrangement of SPOK – 30% Arrangement of the roof – 95% Installation of the splinker system - 5% Building No. 3, section 2: Installation of internal brick walls from the 3rd to 11th floor - 96% Laying of electrical networks (horizontal) for power supply of apartments and boilers, MZK - 97% Installation of NVF - 88% Installation of SPOK - 95% Installation of the roof - 95% Installation of the LMM of the building - 55% Building #3, section 3: Installation of internal brick walls from the 3rd to 34th floor - 99% Installation of fire valves per apartment - 99% Installation of cement-sand screed floor - 97% Installation of NVF - 95% Installation of SPOK - 96% Installation of LMM - 52% Laying of tiles on the floor in MZK - 50% Parking lot No. 3: Installation of the ventilation system B-1-2-3-4-5-6-7-8, P-1 - 78%
Building No. 4, section 1: Construction of concrete structures: 1. Reinforcement and concreting of the floor slab of the 13th floor - 100% 2. Reinforcement and concreting of the vertical elements of the building of the 13th floor - 80%