Construction progress for July 2023

20.07.2023

Go back

METROPOLIS by DIM is under construction!

We share detailed news about the works performed for July:

Building No. 3, Section 1:

  • installation of a cement-sand screed floor - 100%;

  • installation of electrical panels - 35%;

  • installation of internal water supply and sewage systems - 65%;

  • installation of the splinker system - 100%;

  • arrangement of SPOK - 50%;

  • arrangement of the roof - 85%;

  • installation of the 1st elevator - 100%;

  • work on the installation of the pumping station has begun - 10%.

Building No. 3, Section 2:

  • facade works on the outer wall are underway;

  • installation of apartment doors - 70%;

  • arrangement of LMM of the building - 75%;

  • installation of apartment doors - 70%;

  • work on decorating the MZK has begun - 30%;

  • installation of technical doors has begun - 40%;

  • installation of heating systems has begun - 45%;

  • elevator installation - 100%;

  • window glazing - 100%.

Building No. 3, Section 3:

  • installation of internal water supply and sewage systems - 75%;

  • installation of electrical panels - 45%;

  • arrangement of LMM - 75%;

  • laying tiles on the floor in the MZK - 60%;

  • installation of apartment doors - 70%;

  • installation of the 1st elevator - 100%;

  • work on decorating the MZK has begun - 30%;

  • installation of technical doors has begun - 40%;

  • installation of heating systems has begun - 45%.

Railway station parking lot No. 3:

  • arrangement of ventilation system B-1-2-3-4-5-6-7-8, P-1 - 90%.

Building No. 4, Section 1:

  • reinforcement and concreting of the floor slab of the 17th floor - 80%;

  • arrangement of brickwork 8, 9 floors - 100%;

  • installation of staircases on the 15th floor - 100%;

  • installation of ventilation ducts on the 16th floor - 100%.

Building No. 4, Section 2:

  • preparatory works for the installation of the monolith are underway;

  • installation of a retaining wall;

  • we prepare and pour the solution.

Building No. 4, Section 3:

  • reinforcement and concreting of columns of the 8th floor - 100%.

Landscaping:

  • works are being carried out on the improvement of the 1st phase of the 3rd zone.