Construction progress for June 2023

13.06.2023

Go back

METROPOLIS by DIM is under construction! New floors are being built, masonry, facade and interior finishing works are being carried out. We hurry to the growth of the frame of the 4th building and the completion of the construction of the 3rd building.

Building No. 3, section 1: installation of cement-sand screed floor on floors - 95%; installation of electrical panels - 25%; installation of internal water supply systems - 60%; installation of the splinker system - 85%; installation of a drainage system on the facade - 100%; installation of elevator equipment - 25%; sewage installation K1 dept. 4,200 - 75%.

Building No. 3, Section 2:

arrangement of LMM facades; installation of the splinker system - 100%; installation of internal water supply and sewage systems - 70%; installation of electrical panels has begun - 35%; installation of apartment doors - 60%; installation of elevators - 25%; work on decorating the MZK has begun - 20%; installation of technical doors has begun - 10%; installation of heating systems has begun - 30%. Building No. 3, Section 3:

installation of the splinker system - 100%; installation of internal water supply and sewage systems - 70%; installation of electrical panels has begun - 35%; installation of apartment doors - 60%; installation of elevators - 25%; work on decorating the MZK has begun - 20%; installation of technical doors has begun - 10%; installation of heating systems has begun - 30%. Building No. 4, Section 1:

Arrangement of s/b structures: performance of preparatory work for reinforcement and concreting of vertical elements of the 17th floor - 15%; installation of stairs on the 14th floor - 100%; arrangement of internal and external brick walls - 17%; arrangement of brickwork on the 7th-8th floor - 100%.