Construction progress for March 2023
01.04.2022
The modern innovative Metropolis project from the DIM company is actively under construction. We share the latest news from the construction site.
We report on the work done in March:
Building No. 3, Section 1:
completed works on laying heating pipelines for apartments - 98%;
installation of internal water supply and sewage systems - 40%;
installation of a cement-sand screed floor – 83%;
placement of NVF - 85%;
arrangement of SPOK - 42%;
installation of a splinker system - 20%;
installation of elevator equipment - 10%.
Building No. 3, Section 2:
installation of fire valves per apartment - 99%;
arrangement of cement-sand screed floor - 95%;
installation of internal water supply and sewage systems - 50%;
placement of NVF - 95%;
laying tiles on the floor in the MZK - 37%;
installation of a splinker system - 10%;
installation of elevator equipment - 10%.
Building No. 3, Section 3:
arrangement of LMM - 50%;
laying tiles on the floor in the MZK - 50%;
installation of a splinker system - 10%;
installation of elevator equipment - 10%.
Railway station parking lot No. 3:
arrangement of the ventilation system B-1-2-3-4-5-6-7-8, P-1 - 80%;
arrangement of internal brick walls - 90%.
Building No. 4, Section 1:
Installation of reinforced concrete structures:
reinforcement and concreting of vertical elements of the 14th floor building - 80%.
Building No. 4, Section 2:
Preparatory work for monolithic works is underway:
armature brought to the site for the start of monolithic works;
ordered formwork.
Building No. 4, Section 3:
Preparatory work is underway for monolithic works:
partially brought formwork to the construction site;
fittings for the installation of the floor slab were brought to the construction site.