Construction progress for April 2024

30.04.2024

Go back

Metropolis by DIM is being built at a fast pace!

We share the latest news from the construction site for April:

Building No. 3, Section 1:

  • laying electrical networks (horizontal) for lighting MZK - 96%;
  • arrangement of LMM of the building - 90%;
  • installation of elevator equipment - 98%;
  • laying low-current fire networks of MZK and apartments - 91%;
  • laying low-current networks of the access control system (ACS) - 45%.

Building No. 3, Section 2:

  • arrangement of LMM of the building - 97%;
  • installation of elevator equipment - 98%;
  • laying low-current fire networks of MZK and apartments - 96%.

Building No. 3, Section 3:

  • arrangement of LMM - 98%;
  • lining the walls of elevator halls with ceramic tiles - 40%;
  • installation of the fire protection system of the MZK, apartments - 92%;
  • installation of low-current networks of the access control system (ACS) - 60%.

Railway station parking lot No. 3:

  • arrangement of the smoke removal system - 88%;
  • installation of engineering equipment in technical premises - 90%;
  • installation of main lines B1.2-B2.2 – 98%;
  • installation of the fire water supply system - 99%;
  • installation of a low-voltage fire protection system in the parking lot - 75%.

Building No. 4, Section 1:

Arrangement of s/b structures:

  • reinforcement and concreting of horizontal elements of the 24th floor building - 30%;
  • reinforcement and concreting of vertical elements of the building of the 24th floor apartment building - 80%;
  • arrangement of internal and external brick walls - 60%;
  • installation of staircases - 46%.

Building No. 4, Section 3:

Arrangement of s/b structures:

  • reinforcement and concreting of vertical and horizontal elements of the building on the 15th floor - 100%;
  • reinforcement and concreting of the vertical elements of the 16th floor building - 100%;
  • installation of ventilation units - 39%;
  • installation of staircases - 50%.

Railway station #4 parking lot, 2nd line, 2nd start:

  • reinforcement and concreting of horizontal and vertical structures – 52%.