Construction progress for October 2024

11.11.2024

Go back

We share the latest news from the construction site for October:

Building No. 3, Section 1:

  • laying electrical networks (horizontal) for lighting MZK - 98%;
  • arrangement of LMM of the building - 100%;
  • installation of elevator equipment - 100%;
  • laying low-current fire networks of MZK and apartments - 98%;
  • installation of entrance apartment doors - 95%;
  • laying low-current networks of the access control system (ACS) - 85%;
  • insulation and cladding of the fire belt - 100%;
  • arrangement of releases of the lightning protection system of the building - 100%;
  • connecting fans of the smoke extraction system - 70%.

Building No. 3, Section 2:

  • laying low-current fire networks of MZK and apartments - 100%.

Building No. 3, Section 3:

  • arrangement of LMM of the building - 100%;
  • lining the walls of elevator halls with ceramic tiles - 46%;
  • installation of the fire protection system of the MZK, apartments - 99%;
  • installation of low-current LCD networks (access control system) - 90%;
  • installation of water supply meters in apartments - 100%;
  • connecting fans of the smoke removal system - 98%;
  • arrangement of releases of the lightning protection system of the building - 100%.

Railway station parking lot No. 3:

  • arrangement of the smoke removal system - 99%;
  • decoration of the MZK of the basement residential part - 99%;
  • installation of a fire-fighting low-current parking system - 95%;
  • parking lot lighting installation – 95%;
  • arrangement of drainage pits - 100%;
  • installation of horizontal insulation of the fire water main - 90%.

External networks of EO and ETR Railway No. 3:

  • relocation of existing 10 kV overhead lines - 70%;
  • installation of 0.4 kV cable-pipe sewerage in building No. 3 – 17%.

Building No. 4, Section 1:

Arrangement of s/b structures:

  • reinforcement and concreting of vertical elements of the building on the 30th floor - 100%;
  • reinforcement and concreting of horizontal structures of the 31st floor - 50%;
  • arrangement of internal and external brick walls - 73%;
  • installation of staircases - 75%;
  • installation of ventilation units - 70%;
  • arrangement of a facade decoration sample in accordance with the changes - 100%;
  • installation of PVC windows for the arrangement of the facade sample - 100%.

Building No. 4, Section 2:

Arrangement of s/b structures:

  • reinforcement and concreting of vertical elements of the basement part of the building - 100%;
  • reinforcement and concreting of the vertical elements of the building on the 1st floor - 80%;
  • reinforcement and concreting of PP of the 1st floor - 60%.

Building No. 4, Section 3:

Arrangement of s/b structures:

  • installation of ventilation units - 53%;
  • installation of staircases - 55%;
  • arrangement of internal and external brick walls - 35%.

Building No. 4, Section 5:

Arrangement of s/b structures:

  • reinforcement and concreting of vertical and horizontal building elements on the ground floor of the 15th floor - 100%, vertical 16th floor - 80%;
  • arrangement of internal and external brick walls - 18%.

Railway station #4 parking lot (2nd turn, 2nd start):

  • reinforcement and concreting of horizontal and vertical structures - 60%;
  • arrangement of piles - 75%;
  • installation of grills - 67%.