Construction progress for December 2024
08.01.2025
Go back
Sharing the latest updates from the construction site for December:
Building №3, Section 1:
- Installation of apartment entrance doors is completed;
- 50% of radiators have been installed;
- 69% of boilers have been installed.
Building №3, Section 2:
- 75% of balcony railings have been completed;
- 52% of LMM facades have been repaired.
Building №3, Section 3:
- 77% of balcony railings have been completed;
- 23% of LMM facade repairs have been completed.
Parking for Building №3:
- Project solutions for roof drainage have been adjusted;
- Project solutions for roof construction have been adjusted;
- Tender for roof construction has been completed;
- Landscaping concept has been approved, and working documentation is in development.
Building №4, Section 1:
- Brickwork has been completed up to the 22nd floor;
- Installation of ventilation blocks and staircases – 10 floors completed;
- A tender for filling window openings has been conducted, and a contract with the supplier has been signed;
- Tender procedures have begun to select a project organization and contractor for ventilated facades and translucent structures.
Building №4, Section 2:
- Monolithic constructions of the 2nd floor have been completed;
- 100% of the vertical monolithic structures of the 2nd floor have been completed;
- 100% of the horizontal slab of the 2nd floor has been constructed.
Building №4, Section 5:
- Installation of ventilation blocks and staircases has been completed up to the 13th floor inclusively.
Parking for Building №4 (Phase 2, Second Launch):
- The slab of the first section has been 100% completed.
External Networks:
- 81% of the 10kV cable line relocation has been completed;
- Tender procedures have begun to select a project organization for gas supply design for Building №4.