Construction progress for July 2024
30.07.2024
Go back
Metropolis by DIM is being built at a fast pace!
We share the latest news from the construction site for July:
Building No. 3, Section 1:
- laying low-current fire networks of MZK and apartments - 93%;
- installation of entrance apartment doors - 64%;
- laying low-current networks of the access control system (ACS) - 51%;
- insulation and cladding of the fire belt - 82%.
Building No. 3, Section 2:
- arrangement of LMM of the building - 100%;
- installation of elevator equipment - 99%;
- laying low-current fire networks of MZK and apartments - 99%;
- installation of balcony fences - 59%.
Building No. 3, Section 3:
- arrangement of LMM of the building - 99%;
- installation of the fire protection system of the MZK, apartments - 98%;
- installation of low-current LCD networks (access control system) - 77%.
Railway station parking lot No. 3:
- arrangement of the smoke removal system - 94%.
Building No. 4, Section 1:
Arrangement of s/b structures:
- reinforcement and concreting of vertical and horizontal elements of the 26th floor building - 100%;
- reinforcement and concreting of vertical and horizontal elements of the building of the 27th floor - 30%;
- arrangement of internal and external brick walls - 64%;
- installation of staircases - 50%.
Building No. 4, Section 2:
Arrangement of s/b structures:
- reinforcement and concreting of vertical elements of the 1st floor - 60%.
Building No. 4, Section 3:
- installation of staircases - 53%.
Railway station parking lot No. 4 (2nd line, 2nd start):
- reinforcement and concreting of horizontal and vertical structures - 56%;
- installation of grills - 65%.
Railway station #4 parking lot (2nd turn, 4th start):
- arrangement of piles - 35%;
- installation of grills - 12%.