Metropolis by DIM is being built at a fast pace!

We share the latest news from the construction site for February:

Building No. 3, Section 1:

  • laying electrical networks (horizontal) for lighting MZK - 95%;
  • arrangement of SPOK - 99%;
  • arrangement of LMM of the building - 87%;
  • installation of elevator equipment - 96%;
  • laying low-current fire networks of MZK and apartments - 88%;
  • installation of entrance apartment doors - 60%;
  • laying low-current networks of the access control system (ACS) - 15%.

Building No. 3, Section 2:

  • arrangement of LMM of the building - 94%;
  • installation of elevator equipment - 91%;
  • laying low-current fire networks of MZK and apartments - 92%.

Building No. 3, Section 3:

  • arrangement of LMM of the building - 95%;
  • lining the walls of elevator halls with ceramic tiles - 12%;
  • installation of the fire protection system of the MZK, apartments - 87%;
  • installation of the laying of low-current networks of the access control system (ACS) - 25%.

Railway station parking lot No. 3:

  • arrangement of the smoke removal system - 85%;
  • decoration of the MZK of the basement residential part - 99%;
  • installation of engineering equipment in technical premises - 70%;
  • installation of main lines B1.2-B2.2 – 92%;
  • installation of the fire water supply system - 87%;
  • installation of a low-voltage fire protection system in the parking lot - 50%.

Building No. 4, Section 1:

Arrangement of s/b structures:

  • reinforcement and concreting of vertical and horizontal elements of the building of the 22nd floor - 100%;
  • arrangement of internal and external brick walls - 55%;
  • installation of staircases - 43%;
  • installation of ventilation units - 52%.

Building No. 4, Section 3:

Arrangement of s/b structures:

  • reinforcement and concreting of vertical and horizontal elements of the 14th floor building - 100%;
  • installation of ventilation units - 38%;
  • installation of staircases - 29%.

Railway station #4 parking lot, 2nd line, 2nd start-up:

  • reinforcement and concreting of horizontal and vertical structures - 49%.