Construction progress for January 2024

22.01.2024

Go back

Metropolis by DIM is being built at a fast pace!

We share the latest news from the construction site for January:

Building No. 3, Section 1:

  • laying electrical networks (horizontal) for lighting MZK - 90%;
  • arrangement of the NVF - 99%;
  • arrangement of SPOK - 98%;
  • installation of elevator equipment - 95%;
  • laying low-current fire networks of MZK and apartments - 87%;
  • installation of entrance apartment doors - 50%.

Building No. 3, Section 2:

  • arrangement of SPOK - 99%;
  • arrangement of the roof - 99%;
  • arrangement of LMM of the building - 90%;
  • installation of elevator equipment - 90%;
  • laying electrical networks (horizontal) for lighting MZK - 99%;
  • laying low-current fire networks of MZK and apartments - 90%.

Building No. 3, Section 3:

  • arrangement of the NVF - 99%;
  • arrangement of LMM of the building - 90%;
  • laying tiles on the floor in MZK - 100%;
  • lining the walls of elevator halls with ceramic tiles - 10%;
  • installation of the fire protection system of the MZK, apartments - 80%;
  • installation of poorly accurate LCD networks (access control system) - 5%.

Railway station parking lot No. 3:

  • installation of a smoke removal system - 80%;
  • installation of engineering equipment in technical premises - 62%;
  • installation of main lines B1.2-B2.2 – 90%;
  • installation of the fire water supply system - 80%;
  • installation of a low-voltage fire protection system in the parking lot - 40%.

Building No. 4, Section 1:

Arrangement of s/b structures:

  • reinforcement and concreting of vertical and horizontal elements of the building on the 21st floor - 100%;
  • arrangement of internal and external brick walls - 50%;
  • installation of staircases - 40%;
  • installation of ventilation units - 50%.

Building No. 4, Section 3:

Arrangement of s/b structures:

  • reinforcement and concreting of vertical and horizontal elements of the building of the 13th floor - 100%;
  • installation of ventilation units - 30%;
  • installation of staircases - 25%.

Railway station #4 parking lot, 2nd line, 2nd start:

  • reinforcement and concreting of horizontal and vertical structures – 47%.