Construction progress for January 2024
22.01.2024
Go back
Metropolis by DIM is being built at a fast pace!
We share the latest news from the construction site for January:
Building No. 3, Section 1:
- laying electrical networks (horizontal) for lighting MZK - 90%;
- arrangement of the NVF - 99%;
- arrangement of SPOK - 98%;
- installation of elevator equipment - 95%;
- laying low-current fire networks of MZK and apartments - 87%;
- installation of entrance apartment doors - 50%.
Building No. 3, Section 2:
- arrangement of SPOK - 99%;
- arrangement of the roof - 99%;
- arrangement of LMM of the building - 90%;
- installation of elevator equipment - 90%;
- laying electrical networks (horizontal) for lighting MZK - 99%;
- laying low-current fire networks of MZK and apartments - 90%.
Building No. 3, Section 3:
- arrangement of the NVF - 99%;
- arrangement of LMM of the building - 90%;
- laying tiles on the floor in MZK - 100%;
- lining the walls of elevator halls with ceramic tiles - 10%;
- installation of the fire protection system of the MZK, apartments - 80%;
- installation of poorly accurate LCD networks (access control system) - 5%.
Railway station parking lot No. 3:
- installation of a smoke removal system - 80%;
- installation of engineering equipment in technical premises - 62%;
- installation of main lines B1.2-B2.2 – 90%;
- installation of the fire water supply system - 80%;
- installation of a low-voltage fire protection system in the parking lot - 40%.
Building No. 4, Section 1:
Arrangement of s/b structures:
- reinforcement and concreting of vertical and horizontal elements of the building on the 21st floor - 100%;
- arrangement of internal and external brick walls - 50%;
- installation of staircases - 40%;
- installation of ventilation units - 50%.
Building No. 4, Section 3:
Arrangement of s/b structures:
- reinforcement and concreting of vertical and horizontal elements of the building of the 13th floor - 100%;
- installation of ventilation units - 30%;
- installation of staircases - 25%.
Railway station #4 parking lot, 2nd line, 2nd start:
- reinforcement and concreting of horizontal and vertical structures – 47%.