Construction progress for June 2024
24.06.2024
Go back
Metropolis by DIM is being built at a fast pace!
We share the latest news from the construction site for June:
Building No. 3, Section 1:
- arrangement of LMM of the building - 99%;
- installation of entrance apartment doors - 62%;
- laying low-current networks of the access control system (ACS) - 47%;
- insulation and cladding of the fire belt - 80%.
Building No. 3, Section 2:
- arrangement of LMM of the building - 99%;
- installation of elevator equipment - 98%;
- laying low-current fire networks of MZK and apartments - 98%.
Building No. 3, Section 3:
- lining the walls of elevator halls with ceramic tiles - 45%;
- installation of the fire protection system of the MZK, apartments - 96%;
- installation of low-current LCD networks (access control system) - 75%.
Railway station parking lot No. 3:
- arrangement of the smoke removal system - 92%;
- installation of engineering equipment in technical premises - 100%;
- installation of main lines B1.2-B2.2 – 100%;
- installation of the fire water supply system - 100%;
- installation of a low-voltage fire protection system in the parking lot - 85%.
Building No. 4, Section 1:
Arrangement of s/b structures:
- reinforcement and concreting of vertical and horizontal elements of the 25th floor building - 100%;
- reinforcement and concreting of vertical and horizontal elements of the building of the 26th floor - 20%;
- arrangement of internal and external brick walls - 62%;
- installation of staircases - 48%;
- installation of ventilation units - 55%.
Building No. 4, Section 2:
Arrangement of s/b structures:
- reinforcement and concreting of vertical elements of the basement part of the building - 25%.
Building No. 4, Section 3:
- installation of staircases - 52%;
- installation of ventilation units - 50%.
Railway station parking lot No. 4 (2nd line, 2nd start):
- reinforcement and concreting of horizontal and vertical structures - 55%.