Construction progress for March 2024
27.03.2024
Go back
Metropolis by DIM is being built at a rapid pace!
We share the latest news from the construction site for March:
Building No. 3, Section 1:
- arrangement of LMM of the building - 89%;
- installation of elevator equipment - 97%;
- laying low-current fire networks of MZK and apartments - 90%;
- laying low-current networks of the access control system (ACS) - 40%.
Building No. 3, Section 2:
- arrangement of LMM of the building - 96%;
- installation of elevator equipment - 94%;
- laying electrical networks (horizontal) for lighting MZK - 100%;
- laying low-current fire networks of MZK and apartments - 95%.
Building No. 3, Section 3:
- arrangement of LMM of the building - 97%;
- lining the walls of elevator halls with ceramic tiles - 30%;
- installation of the fire protection system of the MZK, apartments - 90%;
- laying low-current networks of the access control system (ACS) - 50%.
Railway station parking lot No. 3:
- installation of engineering equipment in technical premises - 80%;
- installation of main lines B1.2-B2.2 – 97%;
- installation of the fire water supply system - 90%;
- installation of a low-voltage fire protection system in the parking lot - 70%.
Building No. 4, Section 1:
Arrangement of s/b structures:
- reinforcement and concreting of vertical and horizontal elements of the 23rd floor building - 70%;
- reinforcement and concreting of vertical and horizontal elements of the 24th floor building - 20%;
- arrangement of internal and external brick walls - 58%;
- installation of staircases - 45%.
Building No. 4, Section 3:
Arrangement of s/b structures:
- reinforcement and concreting of vertical and horizontal elements of the 15th floor building - 70%;
- reinforcement and concreting of vertical and horizontal elements of the 16th floor building - 20%;
- installation of staircases - 30%.
Railway station #4 parking lot, 2nd line, 2nd start:
- reinforcement and concreting of horizontal and vertical structures - 50%.