Metropolis
Construction progress for May 2024

27.05.2024

Go back

Metropolis by DIM is being built at a rapid pace!

We share the latest news from the construction site for May:

Building No. 3, Section 1:

  • arrangement of LMM of the building - 91%;
  • laying low-current fire networks of MZK and apartments - 92%;
  • installation of entrance apartment doors - 61%;
  • laying low-current networks of the access control system (ACS) - 46%;
  • insulation and lining of the fire belt - 15%.

Building No. 3, Section 2:

  • arrangement of LMM of the building - 98%;
  • laying low-current fire networks of MZK and apartments - 97%.

Building No. 3, Section 3:

  • lining the walls of elevator halls with ceramic tiles - 42%;
  • installation of the fire protection system of the MZK, apartments - 93%;
  • installation of low-current networks of the access control system (ACS) - 61%.

Railway station parking lot No. 3:

  • arrangement of the smoke removal system - 89%;
  • installation of engineering equipment in technical premises - 95%;
  • installation of main lines B1.2-B2.2 – 99%.

Building No. 4, Section 1:

Arrangement of s/b structures:

  • reinforcement and concreting of vertical and horizontal elements of the building on the 24th floor - 100%;
  • reinforcement and concreting of vertical elements of the building on the 25th floor - 20%.

Building No. 4, Section 3:

  • installation of ventilation units - 40%;
  • installation of staircases - 52%.

Railway station #4 parking lot, 2nd line, 2nd start:

  • reinforcement and concreting of horizontal and vertical structures – 53%.