Construction progress for May 2024
27.05.2024
Go back
Metropolis by DIM is being built at a rapid pace!
We share the latest news from the construction site for May:
Building No. 3, Section 1:
- arrangement of LMM of the building - 91%;
- laying low-current fire networks of MZK and apartments - 92%;
- installation of entrance apartment doors - 61%;
- laying low-current networks of the access control system (ACS) - 46%;
- insulation and lining of the fire belt - 15%.
Building No. 3, Section 2:
- arrangement of LMM of the building - 98%;
- laying low-current fire networks of MZK and apartments - 97%.
Building No. 3, Section 3:
- lining the walls of elevator halls with ceramic tiles - 42%;
- installation of the fire protection system of the MZK, apartments - 93%;
- installation of low-current networks of the access control system (ACS) - 61%.
Railway station parking lot No. 3:
- arrangement of the smoke removal system - 89%;
- installation of engineering equipment in technical premises - 95%;
- installation of main lines B1.2-B2.2 – 99%.
Building No. 4, Section 1:
Arrangement of s/b structures:
- reinforcement and concreting of vertical and horizontal elements of the building on the 24th floor - 100%;
- reinforcement and concreting of vertical elements of the building on the 25th floor - 20%.
Building No. 4, Section 3:
- installation of ventilation units - 40%;
- installation of staircases - 52%.
Railway station #4 parking lot, 2nd line, 2nd start:
- reinforcement and concreting of horizontal and vertical structures – 53%.