Construction Progress for January 2025
03.02.2025
Go back
We are sharing the latest updates from the construction site for January:
Building No. 3, Section 1:
- Installation of entrance apartment doors completed;
- Installation of heating radiators on floors 18-20;
- 80% of boilers installed;
- Installation of freight elevators has begun;
- Preparatory work for MZK finishing is underway;
- Work is being carried out on the installation of air ducts and fire protection.
Building No. 3, Section 2:
- 85% of balcony railings completed;
- 60% of LMM facades repaired;
- Preparatory work for MZK finishing is underway;
- Installation of air conditioning baskets completed.
Building No. 3, Section 3:
- 79% of balcony railings completed;
- 35% of LMM facade repairs completed;
- Work on the installation of air ducts and fire protection is underway;
- Work on pipeline thermal insulation is in progress.
Parking of Building No. 3:
- Preparation for roofing work of the parking lot;
- Landscaping concept approved, working documentation is being developed.
Building No. 4, Section 1:
- External brickwork on the 27th floor, internal gas block walls on the 22nd floor;
- Reinforcement of vertical structures on the 31st floor completed;
- Installation of ventilation blocks and staircases – ventilation blocks installed up to the 23rd floor, staircases up to the 28th floor in one riser;
- Agreement signed with the PVC window supplier;
- Tender for the design of NVS and SPOK completed.
Building No. 4, Section 2:
- Reinforcement of the vertical structure completed, and formwork for the horizontal slab on the 4th floor is being installed.
Building No. 4, Section 3:
- Brickwork completed up to the 7th floor after the installation of ventilation blocks;
- Preparatory work is being carried out to extend the tower crane for monolithic horizontal structure works and the fire belt on the 16th floor.
Building No. 4, Section 5:
- Monolithic works on the 15th floor completed;
- Preparatory work for the reconstruction of crane fixing metal structures and extension of the tower crane is underway to continue monolithic works;
- Brickwork completed up to the 5th floor.
Parking of Building No. 4:
- Installation of the bonded beam for retaining wall RM14 – 85% completed;
- Pile installation – 80% completed;
- Excavation and soil removal work continues.
External Networks:
- 86% of the 10 kV cable line relocation completed;
- Tender process underway to select a design organization for the gas supply project of Building No. 4.