Construction Progress for January 2025

03.02.2025

Go back

We are sharing the latest updates from the construction site for January:

Building No. 3, Section 1:

  • Installation of entrance apartment doors completed;
  • Installation of heating radiators on floors 18-20;
  • 80% of boilers installed;
  • Installation of freight elevators has begun;
  • Preparatory work for MZK finishing is underway;
  • Work is being carried out on the installation of air ducts and fire protection.

Building No. 3, Section 2:

  • 85% of balcony railings completed;
  • 60% of LMM facades repaired;
  • Preparatory work for MZK finishing is underway;
  • Installation of air conditioning baskets completed.

Building No. 3, Section 3:

  • 79% of balcony railings completed;
  • 35% of LMM facade repairs completed;
  • Work on the installation of air ducts and fire protection is underway;
  • Work on pipeline thermal insulation is in progress.

Parking of Building No. 3:

  • Preparation for roofing work of the parking lot;
  • Landscaping concept approved, working documentation is being developed.

Building No. 4, Section 1:

  • External brickwork on the 27th floor, internal gas block walls on the 22nd floor;
  • Reinforcement of vertical structures on the 31st floor completed;
  • Installation of ventilation blocks and staircases – ventilation blocks installed up to the 23rd floor, staircases up to the 28th floor in one riser;
  • Agreement signed with the PVC window supplier;
  • Tender for the design of NVS and SPOK completed.

Building No. 4, Section 2:

  • Reinforcement of the vertical structure completed, and formwork for the horizontal slab on the 4th floor is being installed.

Building No. 4, Section 3:

  • Brickwork completed up to the 7th floor after the installation of ventilation blocks;
  • Preparatory work is being carried out to extend the tower crane for monolithic horizontal structure works and the fire belt on the 16th floor.

Building No. 4, Section 5:

  • Monolithic works on the 15th floor completed;
  • Preparatory work for the reconstruction of crane fixing metal structures and extension of the tower crane is underway to continue monolithic works;
  • Brickwork completed up to the 5th floor.

Parking of Building No. 4:

  • Installation of the bonded beam for retaining wall RM14 – 85% completed;
  • Pile installation – 80% completed;
  • Excavation and soil removal work continues.

External Networks:

  • 86% of the 10 kV cable line relocation completed;
  • Tender process underway to select a design organization for the gas supply project of Building No. 4.