Construction progress in August 2025

02.09.2025

Go back

Share the latest news from the construction site for August:

Building #3, section 1:

  • laying ceramic tiles for floors and walls in the common area from the 3rd to the 34th floor - 100%;
  • decorative plastering work in the common area - 100%;
  • painting of ceilings to fit a cube-shaped rail;
  • installation of fire alarm notification system - 100%;
  • work in progress on fire alarm system installation;
  • started work on lobby decoration.

Building #3, section 2:

  • decorative plastering work in the common area - 100%;
  • work in progress on laying ceramic tiles on balconies - 95%.

Building #3, section 3:

  • decorative wall plastering (with painting) from the 6th to the 24th floor - 100%, work in progress on the 25th to 34th floors;
  • laying ceramic tiles for floors and walls in the common area from the 3rd to the 17th floor - 100%, work in progress from the 18th to the 34th floor - 65%.

Parking concrete structure #3:

    waterproofing work ongoing for the parking slab: joint preparation, filling with lightweight concrete, membrane installation, drainage membrane and geotextile, reinforcement of protective slab and concreting. Completion rate — 81%;

    work started on parking floor installation.

Building #4, section 1:

  • installation of roof parapet - 100%;
  • brickwork on walls from the 1st to the 32nd floor - 90%, work in progress from the 33rd to the 34th floor - 50%;
  • elevator equipment installed.

Building #4, section 2:

  • installation of ventilation units - 100%.
  • brickwork on walls from the 2nd to the 7th floor - 100%, work in progress on the 8th floor.

Parking concrete structure #4:

  • work in progress on waterproofing of columns, ramps and ramp slab waterproofing - 40%;
  • work ongoing on vertical structure installation for the parking - 60%, slab floor - 40%.