Construction progress in August 2025
02.09.2025
Go back
Share the latest news from the construction site for August:
Building #3, section 1:
- laying ceramic tiles for floors and walls in the common area from the 3rd to the 34th floor - 100%;
- decorative plastering work in the common area - 100%;
- painting of ceilings to fit a cube-shaped rail;
- installation of fire alarm notification system - 100%;
- work in progress on fire alarm system installation;
- started work on lobby decoration.
Building #3, section 2:
- decorative plastering work in the common area - 100%;
- work in progress on laying ceramic tiles on balconies - 95%.
Building #3, section 3:
- decorative wall plastering (with painting) from the 6th to the 24th floor - 100%, work in progress on the 25th to 34th floors;
- laying ceramic tiles for floors and walls in the common area from the 3rd to the 17th floor - 100%, work in progress from the 18th to the 34th floor - 65%.
Parking concrete structure #3:
waterproofing work ongoing for the parking slab: joint preparation, filling with lightweight concrete, membrane installation, drainage membrane and geotextile, reinforcement of protective slab and concreting. Completion rate — 81%;
work started on parking floor installation.
Building #4, section 1:
- installation of roof parapet - 100%;
- brickwork on walls from the 1st to the 32nd floor - 90%, work in progress from the 33rd to the 34th floor - 50%;
- elevator equipment installed.
Building #4, section 2:
- installation of ventilation units - 100%.
- brickwork on walls from the 2nd to the 7th floor - 100%, work in progress on the 8th floor.
Parking concrete structure #4:
- work in progress on waterproofing of columns, ramps and ramp slab waterproofing - 40%;
- work ongoing on vertical structure installation for the parking - 60%, slab floor - 40%.