Construction Progress for August 2026
03.09.2026
Go back
Sharing the latest construction site updates for August 2026
Building No. 3, Section 1:
- Lobby finishing works are ongoing, including painting works — 85%;
- Painting of staircase walls and ceilings — 25%;
- Finishing works at the parking entrance have been completed.
Building No. 3, Section 2:
- Lobby finishing works are ongoing, including painting works — 80%;
- Tiling of the staircases has been completed — 100%.
Building No. 3, Section 3:
- Installation of large-format wall tiles has been completed — 100%;
- Finishing works at the parking entrance are ongoing;
- Landscaping works in Zone 1 and Zone 2 are underway, including the installation of automatic irrigation and outdoor lighting systems, drainage channels, paving elements and granite curbs, preparation of foundations for COR-TEN retaining walls, and preparation of landscaping areas;
- Installation of on-site water supply, domestic sewage and stormwater drainage networks is underway — 95%;
- Installation of external water supply networks in accordance with Kyivvodokanal technical specifications is underway — 70%;
- Installation of 0.4 kV cables through underground cable ducts — 20%.
Building No. 4, Section 1:
- Installation of PVC windows is underway — 75%;
- Construction of monolithic structures for the fire protection belt (16th floor) is underway — 80%;
- Monolithic works on the roof — 55%.
Building No. 4, Section 2:
- Installation of PVC structures — 15%;
- Roof waterproofing — 10%.
Building No. 4, Section 4:
- Construction of monolithic parking structures and retaining walls is underway;
- Waterproofing of the parking walls is underway.
Building No. 4, Section 5:
- Construction of monolithic parking structures and retaining walls is underway;
- Waterproofing of the parking walls is underway;
- Brickwork has been completed up to the 9th floor.