Construction Progress — October 2026
02.11.2026
Building Ahead — October Progress Update
In Building No. 3, we are completing the lobby finishes. Plumbing fixtures and lighting have already been installed, and furniture and decorative panel installation is now underway. At the same time, we are landscaping the surrounding grounds and working on the utility networks.
In Building No. 4, we continue window installation, reinforced concrete and roofing works, as well as work on the parking garage structures and waterproofing.
Here is an update on construction progress as of the end of October 2026.
Building No. 3, Sections 1, 2 and 3
The lobby is gradually taking shape, with details of the future interior emerging — from lighting to furniture that will create a welcoming space for everyday encounters and coming home.
- We are completing the lobby finishes: plumbing fixtures and lighting have already been installed, and furniture and decorative panel installation has begun.
- Finishing works in all common areas have been fully completed.
- We continue installing handles on apartment entrance doors.
Building No. 3 — Surrounding Grounds
In Zones 1 and 2, landscaping works are underway. We are installing utility systems, paving and preparing the ground for future landscaping.
We continue installing automatic irrigation and outdoor lighting systems, drainage channels, paving elements and granite curbs.
- Foundations for the COR-TEN steel retaining walls have been completed.
- Areas are being prepared for landscaping.
- Installation of on-site water supply, domestic wastewater and stormwater drainage networks is 100% complete.
- External water supply networks, in accordance with the technical specifications of Kyivvodokanal, are 90% complete.
- Installation of 0.4 kV cables in the duct-and-cable system is 70% complete.
Building No. 4, Section 1
Window installation is progressing alongside the construction of reinforced concrete structures in the upper part of the building.
- PVC window installation is 90% complete.
- Construction of the reinforced concrete fire protection belt at the 16th-floor level is 95% complete.
- Reinforced concrete roofing works are 90% complete.
Building No. 4, Section 2
- Installation of PVC structures is ongoing, with 80% of the work completed.
- Roof waterproofing is 25% complete.
Building No. 4, Section 3
- Preparatory works for the next stage of construction were carried out throughout October. Delivery of the window structures is expected.
Building No. 4, Section 4
- We continue constructing the reinforced concrete structures of the parking garage and retaining walls.
- Waterproofing of the parking garage walls is underway to protect the structures from moisture.
Building No. 4, Section 5
- We continue constructing the reinforced concrete structures of the parking garage and retaining walls.
- Waterproofing of the parking garage walls is underway.
- Brickwork has been completed up to and including the 10th floor.
From the building structures to the lighting in the lobby and pathways in the courtyard, every stage is part of creating a future living environment. We continue building and sharing our progress with you.