Construction progress for July 2026
03.08.2026
Sharing the latest construction site updates for July 2026:
Building 3, Section 1
Lobby finishing works are ongoing; painting works – 80% complete;
Installation of large-format wall tiles completed – 100%.
Building 3, Section 2
Lobby finishing works are ongoing; painting works – 70% complete;
Staircase finishing, including tile installation on the stairs – 80% complete.
Building 3, Section 3
Lobby finishing works are ongoing; painting works – 50% complete; large-format wall tiles – 95% complete;
Floor tile installation completed – 100%;
Painting of stairwell walls and ceilings completed – 100%.
Distribution Substation (Power Distribution Point)
Construction of the power distribution point is ongoing:
Installation of the ventilated façade – 90% complete;
Interior finishing and steel structure installation completed; noise protection measures have been completed.
Parking Garage
Parking line marking – 90% complete;
Wheel stopper installation – 95% complete;
Air curtain installation – 80% complete.
Landscaping & External Utility Networks
Landscaping works are underway in Zone 1 and Zone 2;
Installation of on-site water supply, sanitary sewer, and stormwater drainage networks – 95% complete;
Construction of external water supply networks in accordance with Kyivvodokanal technical requirements – 20% complete;
Installation of the cable duct system for 0.4 kV power cables completed – 100%.
Building 4, Section 1
PVC window installation – 65% complete;
Installation of reinforced concrete fire belt structures (16th floor) – 30% complete;
Roof monolithic concrete works – 50% complete;
Brick masonry on the 34th floor – 80% complete.
Building 4, Section 2
Brick masonry at roof level – 85% complete;
PVC window installation – 10% complete.
Building 4, Section 4
Construction of monolithic parking structures and retaining walls is ongoing;
Waterproofing of parking garage walls is underway.
Building 4, Section 5
Construction of monolithic parking structures and retaining walls is ongoing;
Waterproofing of parking garage walls is underway;
Brick masonry completed up to the 8th floor.