Construction progress for July 2026

03.08.2026

Go back

Sharing the latest construction site updates for July 2026:

Building 3, Section 1

  • Lobby finishing works are ongoing; painting works – 80% complete;

  • Installation of large-format wall tiles completed – 100%.

Building 3, Section 2

  • Lobby finishing works are ongoing; painting works – 70% complete;

  • Staircase finishing, including tile installation on the stairs – 80% complete.

Building 3, Section 3

  • Lobby finishing works are ongoing; painting works – 50% complete; large-format wall tiles – 95% complete;

  • Floor tile installation completed – 100%;

  • Painting of stairwell walls and ceilings completed – 100%.

Distribution Substation (Power Distribution Point)

Construction of the power distribution point is ongoing:

  • Installation of the ventilated façade – 90% complete;

  • Interior finishing and steel structure installation completed; noise protection measures have been completed.

Parking Garage

  • Parking line marking – 90% complete;

  • Wheel stopper installation – 95% complete;

  • Air curtain installation – 80% complete.

Landscaping & External Utility Networks

  • Landscaping works are underway in Zone 1 and Zone 2;

  • Installation of on-site water supply, sanitary sewer, and stormwater drainage networks – 95% complete;

  • Construction of external water supply networks in accordance with Kyivvodokanal technical requirements – 20% complete;

  • Installation of the cable duct system for 0.4 kV power cables completed – 100%.

Building 4, Section 1

  • PVC window installation – 65% complete;

  • Installation of reinforced concrete fire belt structures (16th floor) – 30% complete;

  • Roof monolithic concrete works – 50% complete;

  • Brick masonry on the 34th floor – 80% complete.

Building 4, Section 2

  • Brick masonry at roof level – 85% complete;

  • PVC window installation – 10% complete.

Building 4, Section 4

  • Construction of monolithic parking structures and retaining walls is ongoing;

  • Waterproofing of parking garage walls is underway.

Building 4, Section 5

  • Construction of monolithic parking structures and retaining walls is ongoing;

  • Waterproofing of parking garage walls is underway;

  • Brick masonry completed up to the 8th floor.