Construction progress for February 2026

04.03.2026

Go back

Sharing the latest news from the construction site for February 2026:

Building №3, section 1:

  • installation of fire alarm system in progress;
  • ongoing work on lobby decoration, suspended ceilings installation with gypsum plasterboard initiated;
  • tiling on the floors being arranged;
  • ceiling installation with cubiform rail in progress.

Building №3, section 2:

  • ongoing work on lobby decoration, suspended ceilings installation with gypsum plasterboard initiated;
  • tiling on the floors being arranged.

Building №3, section 3:

  • ongoing work on lobby decoration, suspended ceilings installation with gypsum plasterboard initiated;
  • tiling on the floors being arranged.

Work on distribution point construction continued, 100% of monolithic work and 90% of masonry work completed.

Progress on parking floors arrangement of building №3 - 60%

Building №4, section 1:

  • brick masonry basement arrangement in progress.

Building №4, section 2:

  • brick masonry basement arrangement in progress.