Construction progress for February 2026
04.03.2026
Go back
Sharing the latest news from the construction site for February 2026:
Building №3, section 1:
- installation of fire alarm system in progress;
- ongoing work on lobby decoration, suspended ceilings installation with gypsum plasterboard initiated;
- tiling on the floors being arranged;
- ceiling installation with cubiform rail in progress.
Building №3, section 2:
- ongoing work on lobby decoration, suspended ceilings installation with gypsum plasterboard initiated;
- tiling on the floors being arranged.
Building №3, section 3:
- ongoing work on lobby decoration, suspended ceilings installation with gypsum plasterboard initiated;
- tiling on the floors being arranged.
Work on distribution point construction continued, 100% of monolithic work and 90% of masonry work completed.
Progress on parking floors arrangement of building №3 - 60%
Building №4, section 1:
- brick masonry basement arrangement in progress.
Building №4, section 2:
- brick masonry basement arrangement in progress.