Construction progress for May 2026
01.06.2026
Go back
Sharing the latest updates from the construction site for May 2026.
Building No. 3, Section 1:
- Lobby finishing works are ongoing. Installation of suspended moisture-resistant plasterboard ceilings has been completed, and painting works are in progress — 15%.
- Lighting installation in the common areas has been completed — 100%.
- Works on the entrance group facade and facade lighting are in progress — 80%.
Building No. 3, Section 2:
- Lobby finishing works are ongoing. Installation of suspended moisture-resistant plasterboard ceilings has been completed, floor tiling has been completed — 100%, and
- Painting works are in progress — 15%.
- Works on the entrance group facade and facade lighting are in progress — 75%.
- Stair finishing and stair tiling are in progress — 50%.
Building No. 3, Section 3:
- Lobby finishing works are ongoing. Installation of suspended moisture-resistant plasterboard ceilings has been completed — 100%, and plumbing works in the lobby have
- also been completed.
- Works on the entrance group facade and facade lighting are in progress — 80%.
- Installation of cube-shaped slatted ceilings in the common areas has been completed — 100%.
- Works on the construction of the distribution substation are ongoing, and installation of the ventilated facade is in progress — 35%.
- Flooring works in the parking area of Building No. 3 have been completed — 100%. Parking gates and roller shutters have been installed — 100%.
- Landscaping works are ongoing in Zone 1 and Zone 2.
- Installation of on-site water supply, domestic sewage, and stormwater drainage networks is in progress — 70%.
Building No. 4, Section 1:
- PVC window installation works are in progress — 49%.
Building No. 4, Sections 4 and 5:
- Works on the construction of monolithic parking structures and retaining walls are in progress.