Construction progress for March 2026
02.04.2026
Go back
Sharing the latest news from the construction site for March 2026:
Building №3, section 1:
- installation of fire alarm system is in progress;
- lobby decoration, installation of suspended ceilings with gypsum plasterboard, and plumbing works are ongoing;
- tiling on the floors is being installed;
- installation of cuboid rail ceilings in MCC;
- facade arrangement of the entrance group and facade lighting.
Building №3, section 2:
- lobby decoration, installation of suspended ceilings with gypsum plasterboard, and plumbing works are ongoing;
- tiling on the floors is being installed;
- facade arrangement of the entrance group and facade lighting.
Building №3, section 3:
- lobby decoration, installation of suspended ceilings with gypsum plasterboard, and plumbing works are ongoing;
- tiling on the floors is being installed;
- facade arrangement of the entrance group and facade lighting.
Construction works at the substation are ongoing, 90% of masonry works are completed.
Waterproofing works for the underground part and roof are in progress.
Flooring works of parking lot for building №3 are continuing - 80%.
Landscaping works for Zone 1 and Zone 2 near building №3 are ongoing.
Building №4, section 1:
- brickwork installation for the basement is in progress.
Building №4, section 2:
- brickwork installation for the basement is in progress.
Building №4, sections 4, 5:
- monolithic construction works for parking and retaining walls are in progress.