Construction progress in January 2026
28.01.2026
Go back
Sharing the latest news from the construction site for January 2026:
Building No.3, section 1:
- installation of fire alarm system in progress;
- lobby decoration works ongoing, installation of suspended ceilings with GKLW started, 50% of the framework installed;
- tiling on floors - 10%.
Building No.3, section 2:
- lobby decoration works ongoing, installation of suspended ceilings with GKLW started, 20% of the framework installed;
- tiling on floors - 10%;
- installation of lighting fixtures in common areas - 100%.
Building No.3, section 3:
- lobby decoration works ongoing, installation of suspended ceilings with GKLW started, 30% of the framework installed.
Landscaping of Zone 1 of Building No.3:
- earthworks in progress;
- construction of transformer substation, monolithic works - 80%, brickwork - 20%.