support icon
2026
Metropolis
Construction progress in January 2026

28.01.2026

Go back

Sharing the latest news from the construction site for January 2026:

Building No.3, section 1:

  • installation of fire alarm system in progress;
  • lobby decoration works ongoing, installation of suspended ceilings with GKLW started, 50% of the framework installed;
  • tiling on floors - 10%.

Building No.3, section 2:

  • lobby decoration works ongoing, installation of suspended ceilings with GKLW started, 20% of the framework installed;
  • tiling on floors - 10%;
  • installation of lighting fixtures in common areas - 100%.

Building No.3, section 3:

  • lobby decoration works ongoing, installation of suspended ceilings with GKLW started, 30% of the framework installed.

Landscaping of Zone 1 of Building No.3:

  • earthworks in progress;
  • construction of transformer substation, monolithic works - 80%, brickwork - 20%.