Construction progress for April 2023

20.04.2023

Go back

The new Autograph from DIM is under active construction and we are approaching completion. We report with the latest news from the construction site for April:

Building No. 1, section 1:

  • Installation of the ventilated facade of the stylobate part – 95%;

  • Installation of parapet covers for the 7th floor terrace – 100%;

  • Installation of insulation of decorative inserts of the entrance group of the stylobate part (from the parking lot side) – 100%;

  • Disconnection of the electrical panel (in section No. 3) – 70%.

Building No. 1, section 2:

  • Disconnection of the electrical panel (in section No. 3) – 70%.

Building No. 1, section 3:

  • Installation of the ventilated facade of the stylobate part – 95%;

  • Insulation and decoration of cold passages in section No. 3 – 100%;

  • Insulation and decoration of the roof crown – 100%;

  • Installation of insulation of decorative inserts of the entrance group of the stylobate part from the parking lot side – 100%;

  • Connection of K1, K2 to external networks – 100%;

  • Installation of basement lighting – 100%;

  • Electrical panel disconnection – 90%.

House No. 2:

  • Cover installation - 100%;

  • Installation of entrance groups – 100%;

  • Installation of inserts in the finishing frame – 90%;

  • Completion of facade work on the roof – 100%;

  • Plastering work on the stairs to the basement is 100% complete;

  • Plastering of the walls of the parking spaces of reinforced concrete No. 2 – 60%;

  • Installation of fire hydrants and control panel sensors from the 7th to the 26th – 100%;

  • Connection of K1, K2 to external networks – 100%;

  • Laying of power risers supplying floor panels – 100%;

  • Power supply of ShchMU (on the 26th floor) – 90%;

  • Installation of floor panels – 90%;

  • Installation of mortgages for terrace fencing – 100%.

Parking:

  • Parking lot insulation – 80%;

  • Transit of VC pipes - 80%;

  • Preparation of the parking lot floor covering for the installation of the finishing floor – 70%;

  • Installation of waterproofing under finished floors – 15%;

  • Installation of brickwork in special premises – 60%;

  • Fire water supply – 70%;

  • Storm pressure sewerage – 70%;

  • Sprinkler fire extinguishing – 50%.

External networks:

  • Installation of external networks VK, K1, K2 – 100%.