Construction progress for December 2023
26.12.2023
The new Autograph from DIM is finishing construction!
We share a fresh report from the construction site for December:
Building No. 1, section 1:
installation of VC metering units in office premises – 100%;
grounding of the potential equalization system in the basement – 100%;
installation of basement pipe heating systems – 70%;
installation and disconnection of electrical panels in the lobby – 100%;
installation of a gasification system (methane) – 100%.
Building No. 1, section 2:
commissioning of fire extinguishing systems – 100%;
installation of VC metering units in office premises – 100%;
grounding of the potential equalization system in the basement – 100%;
installation of basement pipe heating systems – 100%;
installation and disconnection of electrical panels in the lobby -100%;
installation of a gasification system (methane) – 100%.
Building No. 1, section 3:
installation of water metering units in office premises – 100%;
grounding of the potential equalization system in the basement – 100%;
installation and disconnection of electrical panels in the lobby – 100%;
installation of a gasification system (methane) – 100%.
House No. 2:
installation of air conditioner baskets – 80%;
installation of HVAC, PC, and fire alarm systems in commercial premises – 100%;
installation of railings in stairwells;
installation of ITP – 100%;
boiler room installation – 100%;
installation of electrical panels for built-in premises – 100%;
installation of cable products for built-in premises (lighting in the electrical panel, power supply to the pump panel) – 100%;
grounding of the potential equalization system in the basement – 100%;
installation of smoke exhaust systems in built-in rooms (smoke extraction system) – 100%.
Parking:
installation of a parking roof – 51%;
installation of parking electrical panel – 50%;
installation of drainage pumps – 100%;
installation of ramp heating (section 1, section 3);
pneumatic testing of the sprinkler fire extinguishing system – 100%;
installation of a parking alert system – 100%;
installation of a CO2 and methane gasification system – 100%;
switching off the parking lot's impulse smoke removal fans – 100%;
fire alarm installation – 100%.
External networks:
installation of lighting poles on 26 Kniazya Romana Mstislavycha Street – 100%.
Improvement:
arrangement of improvements on Knyazya Romana Mstislavycha Street (FEM, eco-parking) – 100%;
noise insulation device TP1 – 100%;
installation of gates and grilles – 50%.