Construction progress for October 2023
25.10.2023
We are preparing the new Autograph from DIM for commissioning. We are completing finishing works and landscaping of the territory.
We share a fresh report from the construction site for October:
Building No. 1, section 1:
installation of a cube-shaped MZK rail – 20%;
installation of technical door closers on floors – 100%;
installation of a boiler in the lobby;
commissioning of fire extinguishing systems – 100%;
installation of a potential equalization system – 100%;
installation of sound fire alarms – 100%;
installation of a gasification system (basements) – 100%.
Building No. 1, section 2:
installation of technical door closers on floors – 100%;
installation of sanitary ware in the lobby (toilet, washbasin mixer and washbasin);
installation of a boiler in the lobby;
installation of a potential equalization system – 100%;
installation of a gasification system (basements) – 100%.
Building No. 1, section 3:
installation of a cube-shaped MZK rail – 100%;
installation of technical door closers on floors – 100%;
installation of sanitary ware in the lobby (toilet, washbasin mixer and washbasin);
commissioning of fire extinguishing systems – 70%;
installation of a potential equalization system – 100%;
installation of a gasification system (basements) – 100%.
House No. 2:
installation of technical door closers on floors – 100%;
installation of the facade of the 1st and 2nd floors – 100%;
installation of air conditioner baskets – 65%;
installation of ITP – 90%;
boiler room installation – 30%;
installation of a boiler in the lobby;
installation of thermostatic radiator heads in apartments – 100%;
pneumatic testing of the water supply system, purified water supply system, fire water supply system, heating system – 100%.
Parking:
parking lot painting – 75%;
installation of a water supply and drainage system in the boiler room – 100%;
installation of a gasification system – 90%.
External networks:
laying of an artesian water pipeline – 100%;
installation of waterproofing of the cable floor – 100%.