Construction progress for October 2023

25.10.2023

Go back

We are preparing the new Autograph from DIM for commissioning. We are completing finishing works and landscaping of the territory.

We share a fresh report from the construction site for October:

Building No. 1, section 1:

  • installation of a cube-shaped MZK rail – 20%;

  • installation of technical door closers on floors – 100%;

  • installation of a boiler in the lobby;

  • commissioning of fire extinguishing systems – 100%;

  • installation of a potential equalization system – 100%;

  • installation of sound fire alarms – 100%;

  • installation of a gasification system (basements) – 100%.

Building No. 1, section 2:

  • installation of technical door closers on floors – 100%;

  • installation of sanitary ware in the lobby (toilet, washbasin mixer and washbasin);

  • installation of a boiler in the lobby;

  • installation of a potential equalization system – 100%;

  • installation of a gasification system (basements) – 100%.

Building No. 1, section 3:

  • installation of a cube-shaped MZK rail – 100%;

  • installation of technical door closers on floors – 100%;

  • installation of sanitary ware in the lobby (toilet, washbasin mixer and washbasin);

  • commissioning of fire extinguishing systems – 70%;

  • installation of a potential equalization system – 100%;

  • installation of a gasification system (basements) – 100%.

House No. 2:

  • installation of technical door closers on floors – 100%;

  • installation of the facade of the 1st and 2nd floors – 100%;

  • installation of air conditioner baskets – 65%;

  • installation of ITP – 90%;

  • boiler room installation – 30%;

  • installation of a boiler in the lobby;

  • installation of thermostatic radiator heads in apartments – 100%;

  • pneumatic testing of the water supply system, purified water supply system, fire water supply system, heating system – 100%.

Parking:

  • parking lot painting – 75%;

  • installation of a water supply and drainage system in the boiler room – 100%;

  • installation of a gasification system – 90%.

External networks:

  • laying of an artesian water pipeline – 100%;

  • installation of waterproofing of the cable floor – 100%.