Construction progress for November 2023
22.11.2023
The new Autograph from DIM is finishing construction!
We share a fresh report from the construction site for November:
Building No. 1, section 1:
installation of a cube-shaped MZK rail – 50%.
Building No. 1, section 2:
commissioning of fire extinguishing systems – 90%.
Building No. 1, section 3:
commissioning of fire extinguishing systems – 100%.
House No. 2:
installation of air conditioner baskets – 70%;
installation of a parapet cover for the terrace of the 3rd floor of reinforced concrete building No. 2 – 100%;
installation of floor screed in the electrical panel of non-residential premises of reinforced concrete building No. 2 – 100%;
installation of painting of walls and ceilings in the electrical panel of non-residential premises of ZHB No. 2 – 100%;
installation of ITP – 95%;
boiler room installation – 90%;
elevator shaft decoration – 80%.
Parking:
installation of a parking lot roof slope (expanded clay concrete) – 50%;
installation of fire cabinets – 100%;
installation of a fire alarm system -100%;
installation of illuminated devices – 100%;
installation of electrical panels (fan control panels and lighting panels) – 100%.
External networks:
laying of outdoor lighting cable at 26 Kniazya Romana Mstislavycha Street (laying of sleeves, cable, electrical wells) – 100%.
Improvement:
improvement of Knyazya Romana Mstislavych Street – 60%;
installation of automatic irrigation systems on Knyazya Romana Mstislavycha Street – 100%;
installation of mortgages for decorative lighting on Knyazya Romana Mstislavycha Street – 100%;
arrangement of fields TP1, TP2 with embedded parts – 100%;
Installation of painting of walls and ceilings TP1, TP2 – 100%.