Construction progress for November 2023

22.11.2023

Go back

The new Autograph from DIM is finishing construction!

We share a fresh report from the construction site for November:

Building No. 1, section 1:

  • installation of a cube-shaped MZK rail – 50%.

Building No. 1, section 2:

  • commissioning of fire extinguishing systems – 90%.

Building No. 1, section 3:

  • commissioning of fire extinguishing systems – 100%.

House No. 2:

  • installation of air conditioner baskets – 70%;

  • installation of a parapet cover for the terrace of the 3rd floor of reinforced concrete building No. 2 – 100%;

  • installation of floor screed in the electrical panel of non-residential premises of reinforced concrete building No. 2 – 100%;

  • installation of painting of walls and ceilings in the electrical panel of non-residential premises of ZHB No. 2 – 100%;

  • installation of ITP – 95%;

  • boiler room installation – 90%;

  • elevator shaft decoration – 80%.

Parking:

  • installation of a parking lot roof slope (expanded clay concrete) – 50%;

  • installation of fire cabinets – 100%;

  • installation of a fire alarm system -100%;

  • installation of illuminated devices – 100%;

  • installation of electrical panels (fan control panels and lighting panels) – 100%.

External networks:

  • laying of outdoor lighting cable at 26 Kniazya Romana Mstislavycha Street (laying of sleeves, cable, electrical wells) – 100%.

Improvement:

  • improvement of Knyazya Romana Mstislavych Street – 60%;

  • installation of automatic irrigation systems on Knyazya Romana Mstislavycha Street – 100%;

  • installation of mortgages for decorative lighting on Knyazya Romana Mstislavycha Street – 100%;

  • arrangement of fields TP1, TP2 with embedded parts – 100%;

  • Installation of painting of walls and ceilings TP1, TP2 – 100%.