Novyi Autograph
Construction progress for August 2023

23.08.2023

Go back

The new Autograph from DIM is actively moving towards completion.

We share the latest news from the construction site for July:

Building No. 1, section 1:

  • Installation of apartment trim – 100%

  • Installation of basement lighting – 100%

  • Fire cabinet assembly – 100%

  • Installation of stairwell railings – 50%

  • Arrangement between balcony screens of terraces Section 1 floor 7th - 90%

  • Installation of fire detectors – 95%

Building No. 1, section 2:

  • Staircase Painting -100%

  • Installation of apartment trim – 100%

  • Installation of fire door trim in the stairwell – 20%

  • Installation of stairwell railings – 90%

  • Installation of fire detectors – 95%

Building No. 1, section 3:

  • MZK painting -100%

  • Staircase painting -100%

  • Installation of a cuboid rail – 30%

  • Installation of apartment trim – 100%

  • Installation of apartment electric meters – 100%

  • Installation of fire detectors – 95%

House No. 2:

  • MZK painting -100%

  • Cuboid rail installation – 45%

  • Lobby decoration – 90%

  • Installation of decorative elements of the facade of reinforced concrete building No. 2 1.2 floors -80%

  • SCANROC system installation – 80%

  • Installation of air conditioner brackets 1,2 floors – 100%

  • Insulation of the 1st and 2nd floors, SCANROC installation area – 100%

  • Installation of the 22nd-26th floor -100%

  • Installation of built-in pumping stations – 90%

  • Installation of apartment trim – 90%

  • Installation of stairwell lights – 100%

  • Installation of apartment electric meters – 80%

  • Power supply to the cellars in the basement – 100%

  • Installation of apartment electrical panels -30%

  • Fire cabinets assembly – 100%

  • Installation of a fire engine connection point -100%

  • Terrace fencing installation Section 2 -100%

  • Installation of embedded parts under translucent canopies (Darnitsa side)

  • Lightning protection installation – 100%

  • Installation of fire detectors – 90%

  • Sprinkler fire extinguishing of the barn -100%

Parking:

  • Installation of a clean floor Parking - 89%

  • Installation of waterproofing in the Parking lot -89%

  • Installation of ramp C3 in the parking lot

  • Installation of a concrete light well

  • Installation of external and internal doors – 70%

  • Installation of electrical networks -30%

  • Storm pressure sewerage – 80%

Improvement:

  • Roadway construction (KUTEP zone) -50%