Construction progress for August 2023
23.08.2023
The new Autograph from DIM is actively moving towards completion.
We share the latest news from the construction site for July:
Building No. 1, section 1:
Installation of apartment trim – 100%
Installation of basement lighting – 100%
Fire cabinet assembly – 100%
Installation of stairwell railings – 50%
Arrangement between balcony screens of terraces Section 1 floor 7th - 90%
Installation of fire detectors – 95%
Building No. 1, section 2:
Staircase Painting -100%
Installation of apartment trim – 100%
Installation of fire door trim in the stairwell – 20%
Installation of stairwell railings – 90%
Installation of fire detectors – 95%
Building No. 1, section 3:
MZK painting -100%
Staircase painting -100%
Installation of a cuboid rail – 30%
Installation of apartment trim – 100%
Installation of apartment electric meters – 100%
Installation of fire detectors – 95%
House No. 2:
MZK painting -100%
Cuboid rail installation – 45%
Lobby decoration – 90%
Installation of decorative elements of the facade of reinforced concrete building No. 2 1.2 floors -80%
SCANROC system installation – 80%
Installation of air conditioner brackets 1,2 floors – 100%
Insulation of the 1st and 2nd floors, SCANROC installation area – 100%
Installation of the 22nd-26th floor -100%
Installation of built-in pumping stations – 90%
Installation of apartment trim – 90%
Installation of stairwell lights – 100%
Installation of apartment electric meters – 80%
Power supply to the cellars in the basement – 100%
Installation of apartment electrical panels -30%
Fire cabinets assembly – 100%
Installation of a fire engine connection point -100%
Terrace fencing installation Section 2 -100%
Installation of embedded parts under translucent canopies (Darnitsa side)
Lightning protection installation – 100%
Installation of fire detectors – 90%
Sprinkler fire extinguishing of the barn -100%
Parking:
Installation of a clean floor Parking - 89%
Installation of waterproofing in the Parking lot -89%
Installation of ramp C3 in the parking lot
Installation of a concrete light well
Installation of external and internal doors – 70%
Installation of electrical networks -30%
Storm pressure sewerage – 80%
Improvement:
Roadway construction (KUTEP zone) -50%