Novyi Autograph
Construction progress for February 2023

26.12.2024

Go back

The new Autograph from DIM is ready for commissioning. The final stages of completing the electrical panels, fire extinguishing systems, and apartment decoration are 100% ready.

We share the latest news from the construction site for the month of February:

Building No. 1, section 1:

  • Complete set of fire cabinets (without a drum for a crane f25, fire hoses and barrels) – 100%;

  • Installation of apartment electrical panels – 100%;

  • disconnection of smoke exhaust fan motor control panels on the roof – 100%;

  • Dispatching of engineering equipment — 90%.

Building No. 1, section 2:

  • Complete set of fire cabinets (without a drum for a crane f25, fire hoses and barrels) – 100%;

  • disconnection of smoke exhaust fan motor control panels on the roof – 100%;

  • Dispatching of engineering equipment – 90%.

Building No. 1, section 3:

  • Complete set of fire cabinets (without a drum for a crane f25, fire hoses and barrels) – 100%;

  • Dispatching of engineering equipment – 90%.

House No. 2:

  • Installation of water meters – 100%;

  • Installation of electrical networks in the lobby – 100%;

  • Installation of tiles on stairwells for general use – 95%;

  • Setting the reinforcement of the balconies of the HP - 100%;

  • Dispatching of engineering equipment – 90%.

Parking:

  • Dispatching of engineering equipment – 90%.

External networks:

  • Work has begun on configuring external networks VK, K1, K2 (from the side of the KUTEP dormitory).