Novyi Autograph
Construction progress for June 2023

14.06.2023

Go back

The new Autograph from DIM is preparing for completion.

We share the latest news from the construction site for June:

Building No. 1, section 1:

  • Installation of waterproofing of balconies on residential buildings – 100%;

  • Installation of tiles on the balconies of residential buildings – 100%;

  • MZK painting device – 80%;

  • Lobby decoration – 100%;

  • Installation of boilers in office premises – 100%;

  • Installation of built-in lights and motion sensors MZK – 100%;

  • Installation of stairwell lights – 100%;

  • Installation of apartment electric meters – 65%;

  • Installation of lightning protection – 100%;

  • Installation of fire safety detectors – 90%.

Building No. 1, section 2:

  • MZK painting – 100%;

  • Staircase painting – 90%;

  • Lobby decoration – 100%;

  • Ceiling insulation under the lobby (from the basement) – 100%;

  • Installation of built-in lights and motion sensors MZK – 100%;

  • Installation of stairwell lights – 100%;

  • Installation of apartment electric meters – 100%;

  • Installation of lightning protection – 100%;

  • Installation of fire safety detectors – 90%.

Building No. 1, section 3:

  • MZK painting – 80%;

  • Staircase cell staining – 90%;

  • Installation of tiles on the balcony of the residential building – 30%;

  • Lobby decoration – 100%;

  • Installation of apartment trim – 95%;

  • Installation of railings on staircases – 90%;

  • Installation of boilers in office premises – 100%;

  • Installation of fencing of the HP – 100%;

  • Installation of built-in lights and motion sensors MZK – 100%;

  • Installation of stairwell lights – 100%;

  • Installation of apartment electric meters – 65%;

  • Installation of lightning protection – 100%;

  • Installation of fire safety detectors – 90%.

House No. 2:

  • MZK painting – 60%;

  • Painting of the “warm” stairwell – 100%;

  • Installation of tiles on balconies of residential buildings – 50%;

  • Installing a cube-shaped rail on the ceiling – 40%;

  • Lobby decoration – 60%;

  • Installation of the 22nd-26th floor (KUTEP side) – 100%;

  • Installation of slopes from the ACP in the 22nd-26th floors of the NWF (parking lot side) – 100%;

  • Installation of the 22nd-26th floors (KUTEP side) – 85%;

  • Installation of decorative elements of the facade of reinforced concrete building No. 2, 1st and 2nd floors – 40% (KUTEP side);

  • Installation of the SCANROC system (KUTEP side) – 50%;

  • Installation of the SCANROC system (end of reinforced concrete block No. 2 towards Darnytsia) – 35%;

  • Installation of the SCANROC system (inner courtyard) – 35%;

  • Installation of apartment trim – 15%;

  • Establishment of audit of EA – 100%;

  • Installation of a domestic pumping system – 90%;

  • Installation of pumping stations in built-in premises – 30%;

  • Installation of fencing of the HP – 100%.

Parking:

  • Installation of a clean parking floor – 60%;

  • Ceiling painting – 40%;

  • Installation of pump sprinkler fire extinguishing system – 95%.