Construction progress for June 2023
14.06.2023
The new Autograph from DIM is preparing for completion.
We share the latest news from the construction site for June:
Building No. 1, section 1:
Installation of waterproofing of balconies on residential buildings – 100%;
Installation of tiles on the balconies of residential buildings – 100%;
MZK painting device – 80%;
Lobby decoration – 100%;
Installation of boilers in office premises – 100%;
Installation of built-in lights and motion sensors MZK – 100%;
Installation of stairwell lights – 100%;
Installation of apartment electric meters – 65%;
Installation of lightning protection – 100%;
Installation of fire safety detectors – 90%.
Building No. 1, section 2:
MZK painting – 100%;
Staircase painting – 90%;
Lobby decoration – 100%;
Ceiling insulation under the lobby (from the basement) – 100%;
Installation of built-in lights and motion sensors MZK – 100%;
Installation of stairwell lights – 100%;
Installation of apartment electric meters – 100%;
Installation of lightning protection – 100%;
Installation of fire safety detectors – 90%.
Building No. 1, section 3:
MZK painting – 80%;
Staircase cell staining – 90%;
Installation of tiles on the balcony of the residential building – 30%;
Lobby decoration – 100%;
Installation of apartment trim – 95%;
Installation of railings on staircases – 90%;
Installation of boilers in office premises – 100%;
Installation of fencing of the HP – 100%;
Installation of built-in lights and motion sensors MZK – 100%;
Installation of stairwell lights – 100%;
Installation of apartment electric meters – 65%;
Installation of lightning protection – 100%;
Installation of fire safety detectors – 90%.
House No. 2:
MZK painting – 60%;
Painting of the “warm” stairwell – 100%;
Installation of tiles on balconies of residential buildings – 50%;
Installing a cube-shaped rail on the ceiling – 40%;
Lobby decoration – 60%;
Installation of the 22nd-26th floor (KUTEP side) – 100%;
Installation of slopes from the ACP in the 22nd-26th floors of the NWF (parking lot side) – 100%;
Installation of the 22nd-26th floors (KUTEP side) – 85%;
Installation of decorative elements of the facade of reinforced concrete building No. 2, 1st and 2nd floors – 40% (KUTEP side);
Installation of the SCANROC system (KUTEP side) – 50%;
Installation of the SCANROC system (end of reinforced concrete block No. 2 towards Darnytsia) – 35%;
Installation of the SCANROC system (inner courtyard) – 35%;
Installation of apartment trim – 15%;
Establishment of audit of EA – 100%;
Installation of a domestic pumping system – 90%;
Installation of pumping stations in built-in premises – 30%;
Installation of fencing of the HP – 100%.
Parking:
Installation of a clean parking floor – 60%;
Ceiling painting – 40%;
Installation of pump sprinkler fire extinguishing system – 95%.