Construction progress for March 2023
21.03.2023
The new Autograph from DIM is actively being built, with finishing works and parking construction in the final stages. We are in a hurry to hand over the keys to the future apartment owners as soon as possible.
We share the latest news from the construction site for March: Building No. 1, section 1: Installation of the ventilated facade on the stylobate – 85%; Installation of the parapet cover of the 7th floor terrace – 95%. Building No. 1, section 2: Dispatching of engineering equipment – 96%. Building No. 1, section 3: Installation of a ventilated facade on the stylobate – 80%; Installation of the roof parapet cover frame – 100%; Installation of the cover – 50%; Installation of basement lighting – 30%; Disconnection of the electrical panel – 50%; Installation of marble in the lobby – 70%. House No. 2: Installation of the roof parapet cover frame – 100%, installation of the cover – 60%; Electricity supply to apartments – 100%; Installation of trays in the basement for electrical networks – 100%. Parking: Installation of waterproofing under the power plate – 5%; Installation of the parking lot power plate (under technical rooms) – 5%; Installation of the VK main – 50%; Fire water supply – 40%; Storm pressure sewerage – 35%; Parking lot smoke removal – 95%.
External networks: Installation of external networks VK, K1, K2 – 90%.