Construction progress for May 2023
09.05.2023
The new Autograph from DIM is actively being built for full completion.
We share the latest news from the construction site for May:
Building No. 1, section 2:
Insulation and decoration of the entrance hall ceiling from the outside
Ceiling insulation under the lobby (from the basement) – 80%
MZK painting – 40%
Staircase painting – 40%
Tile installation on HP – 100%
Installation of boilers in office premises - 100%
Lobby decoration – 75%
Electrical panel disconnection – 100%
Installation of basement lighting – 90%
Installation of MZK lamps – 30%
Installation of lobby lights – 50%
Lightning protection installation – 90%
Installation of fire protection system equipment – 25%
Building No. 1, section 3:
Insulation and decoration of the entrance hall ceiling from the outside
MZK painting – 40%
Installation of cube-shaped ceiling rail – 30%
Installation of boilers in office premises – 25%
Lobby decoration – 80%
Installation of HP drains – 100%
Terrace and screen fencing – 100%
Fencing of the HP – 50%
Installation of brackets for translucent canopies – 100%
Manufacturing of metal structures for canopies – 100%
Electrical panel disconnection – 100%
Installation of MZK lamps – 30%
Installation of lobby lights – 50%
Lightning protection installation – 90%
Installation of fire protection system equipment – 25%
House No. 2:
Installation of decorative elements of the facade 1st, 2nd floors – 20% (KUTEP side)
Installation of NWV from 22-26 floors (KUTEP side) – 90%
Installation of inserts in the NVF decoration 22-26th (KUTEP side) – 100%
Installation of inserts in the NVF decoration 22-26th (parking lot side) – 100%
Installation of slopes from the ACP in the 22nd-26th floors of the NWF (parking lot side) – 35%
MZK painting – 30%
Fire cabinets complete set – 70%
Installation of a domestic pumping system – 60%
Lobby decoration – 35%
Installation of HP drains – 100%
Installation of brackets for translucent canopies – 100%
Manufacturing of metal structures for canopies – 100%
Installation of floor panels – 100%
Installation of MZK lamps – 20%
Installation of electrical panel – 90%
Installation of basement lighting – 50%
Installation of aluminum doors from the 3rd to the 26th - 100%
Installation of fire protection system equipment – 25%
Parking:
Installation of a clean parking floor – 30%
Insulation of parking space walls – 100%
Transit of VC pipes - 100%
Transit of the heating system of ZhB No. 2 – 100%
Artesian water pipe jumper from pumping station No. 2 to pumping station No. 1 – 100%
Sprinkler fire extinguishing – 75%
Electric lighting installation – 10%