Construction progress for May 2023

09.05.2023

Go back

The new Autograph from DIM is actively being built for full completion.

We share the latest news from the construction site for May:

Building No. 1, section 2:

  • Insulation and decoration of the entrance hall ceiling from the outside

  • Ceiling insulation under the lobby (from the basement) – 80%

  • MZK painting – 40%

  • Staircase painting – 40%

  • Tile installation on HP – 100%

  • Installation of boilers in office premises - 100%

  • Lobby decoration – 75%

  • Electrical panel disconnection – 100%

  • Installation of basement lighting – 90%

  • Installation of MZK lamps – 30%

  • Installation of lobby lights – 50%

  • Lightning protection installation – 90%

  • Installation of fire protection system equipment – 25%

Building No. 1, section 3:

  • Insulation and decoration of the entrance hall ceiling from the outside

  • MZK painting – 40%

  • Installation of cube-shaped ceiling rail – 30%

  • Installation of boilers in office premises – 25%

  • Lobby decoration – 80%

  • Installation of HP drains – 100%

  • Terrace and screen fencing – 100%

  • Fencing of the HP – 50%

  • Installation of brackets for translucent canopies – 100%

  • Manufacturing of metal structures for canopies – 100%

  • Electrical panel disconnection – 100%

  • Installation of MZK lamps – 30%

  • Installation of lobby lights – 50%

  • Lightning protection installation – 90%

  • Installation of fire protection system equipment – 25%

House No. 2:

  • Installation of decorative elements of the facade 1st, 2nd floors – 20% (KUTEP side)

  • Installation of NWV from 22-26 floors (KUTEP side) – 90%

  • Installation of inserts in the NVF decoration 22-26th (KUTEP side) – 100%

  • Installation of inserts in the NVF decoration 22-26th (parking lot side) – 100%

  • Installation of slopes from the ACP in the 22nd-26th floors of the NWF (parking lot side) – 35%

  • MZK painting – 30%

  • Fire cabinets complete set – 70%

  • Installation of a domestic pumping system – 60%

  • Lobby decoration – 35%

  • Installation of HP drains – 100%

  • Installation of brackets for translucent canopies – 100%

  • Manufacturing of metal structures for canopies – 100%

  • Installation of floor panels – 100%

  • Installation of MZK lamps – 20%

  • Installation of electrical panel – 90%

  • Installation of basement lighting – 50%

  • Installation of aluminum doors from the 3rd to the 26th - 100%

  • Installation of fire protection system equipment – 25%

Parking:

  • Installation of a clean parking floor – 30%

  • Insulation of parking space walls – 100%

  • Transit of VC pipes - 100%

  • Transit of the heating system of ZhB No. 2 – 100%

  • Artesian water pipe jumper from pumping station No. 2 to pumping station No. 1 – 100%

  • Sprinkler fire extinguishing – 75%

  • Electric lighting installation – 10%