Construction progress for September 2023
21.09.2023
The new Autograph from DIM is actively being built.
We share a fresh report from the construction site for September:
Building No. 1, section 1:
Installation of sanitary ware in the lobby (toilet, washbasin mixer and washbasin);
Installation of rotor nuts for connecting fire engines – 100%;
Complete set of fire cabinets in office premises – 95%;
Installation of cold junction luminaires – 100%;
Connecting apartments to Internet networks using PON technology (optical fiber is pulled into each apartment).
Building No. 1, section 2:
Polishing of the marble floor of the lobby – 100%;
Installation of rotor nuts for connecting fire engines – 100%;
Complete set of fire cabinets in office premises – 95%;
Installation of cold junction luminaires – 100%;
Connecting apartments to Internet networks using PON technology (optical fiber is pulled into each apartment);
Fire protection systems setup – 100%.
Building No. 1, section 3:
Installation of a cubic rail of the MZK – 70%;
Installation of rotor nuts for connecting fire engines – 100%;
Complete set of fire cabinets in office premises – 95%;
Installation of cold junction luminaires – 100%;
Installation of water drainage from K13 (sewerage from air conditioners) to the green zone – 100%;
Connecting apartments to Internet networks using PON technology (optical fiber is pulled into each apartment);
Installation of sound fire alarms – 100%.
House No. 2:
Installation of the facade of the 1st and 2nd floors – 85%;
Installation of thermostatic heads on apartment radiators – 100%;
Installation of sanitary ware in the lobby (toilet, washbasin mixer and washbasin);
Installation of cold junction lights – 30%;
Connecting apartments to Internet networks using PON technology (optical fiber is pulled into each apartment);
Installation of sound fire alarms – 100%.
Parking:
Installation of a clean parking floor – 100%;
Parking lot painting – 65%;
Installation of electrical networks – 60%;
Installation of storm sewer K2 – 95%;
Sprinkler fire extinguishing installation – 100%.
Improvement:
Arrangement of the roadway (KUTEP zone) – 90%;
Installation of a blind area from the side of Knyazya Romana Mstislavycha Street, 26 – 90%.