The new Autograph from DIM is actively being built.

We share a fresh report from the construction site for September:

Building No. 1, section 1:

  • Installation of sanitary ware in the lobby (toilet, washbasin mixer and washbasin);

  • Installation of rotor nuts for connecting fire engines – 100%;

  • Complete set of fire cabinets in office premises – 95%;

  • Installation of cold junction luminaires – 100%;

  • Connecting apartments to Internet networks using PON technology (optical fiber is pulled into each apartment).

Building No. 1, section 2:

  • Polishing of the marble floor of the lobby – 100%;

  • Installation of rotor nuts for connecting fire engines – 100%;

  • Complete set of fire cabinets in office premises – 95%;

  • Installation of cold junction luminaires – 100%;

  • Connecting apartments to Internet networks using PON technology (optical fiber is pulled into each apartment);

  • Fire protection systems setup – 100%.

Building No. 1, section 3:

  • Installation of a cubic rail of the MZK – 70%;

  • Installation of rotor nuts for connecting fire engines – 100%;

  • Complete set of fire cabinets in office premises – 95%;

  • Installation of cold junction luminaires – 100%;

  • Installation of water drainage from K13 (sewerage from air conditioners) to the green zone – 100%;

  • Connecting apartments to Internet networks using PON technology (optical fiber is pulled into each apartment);

  • Installation of sound fire alarms – 100%.

House No. 2:

  • Installation of the facade of the 1st and 2nd floors – 85%;

  • Installation of thermostatic heads on apartment radiators – 100%;

  • Installation of sanitary ware in the lobby (toilet, washbasin mixer and washbasin);

  • Installation of cold junction lights – 30%;

  • Connecting apartments to Internet networks using PON technology (optical fiber is pulled into each apartment);

  • Installation of sound fire alarms – 100%.

Parking:

  • Installation of a clean parking floor – 100%;

  • Parking lot painting – 65%;

  • Installation of electrical networks – 60%;

  • Installation of storm sewer K2 – 95%;

  • Sprinkler fire extinguishing installation – 100%.

Improvement:

  • Arrangement of the roadway (KUTEP zone) – 90%;

  • Installation of a blind area from the side of Knyazya Romana Mstislavycha Street, 26 – 90%.