Construction progress for August 2025
03.09.2025
Go back
In August 2025, the following works were carried out at the construction site:
Section 1:
- Laying of cement-sand screed from the 2nd to the 8th floor - 100%
- Facade installation - 10%
- Sound insulation, floor installation in apartments, waterproofing in bathrooms and balconies, as well as preparation for laying cement screed from the 2nd to the 8th floor - 100%
- Installation of internal engineering systems for floor heating/water supply, electrical supply of low-current networks in apartments and common areas from the 2nd to the 8th floor - 100%
- Installation of ventilation shafts (covers) - 100%
- Installation of elevator equipment - 20%
Section 2:
- Masonry of external and internal partition walls: 4, 6-8 floors - 100%
- Window installation: 1st floor - 95%, 2nd and 4th floors - 100%
- Installation of water supply risers - 20%
- Installation of ventilation shafts (covers) - 100%
- Foundation construction on the existing roof
Section 3:
- Foundation construction on the existing roof
- Installation of ventilation shafts (covers) - 100%
- Facade installation - 10%
- Installation of heating risers for stairwells - 100%
Section 4:
- Masonry of external and internal partition walls: 2nd floor - 100%
- Sound insulation, floor installation in apartments, waterproofing in bathrooms and balconies, as well as preparation for laying cement screed - 90%
- Installation of water supply risers - 75%
- Installation of ventilation shafts (covers) - 100%
- Foundation construction on the existing roof
- Installation of internal engineering networks for electrical heating in apartments and common areas - 20%
- Installation of internal engineering networks for water supply, sewage, and storm drainage - 20%
Section 5:
- Masonry of external and internal partition walls: 2nd floor - 100%
- Sound insulation, floor installation in apartments, waterproofing in bathrooms and balconies, as well as preparation for laying cement screed from the 2nd to the 8th floor - 100%
- Installation of internal engineering networks for electrical heating in apartments and common areas - 80%
- Installation of internal engineering networks for water supply, sewage, and storm drainage - 80%
- Facade installation - 5%
- Installation of ventilation shafts (covers) - 100%
- Laying of cement-sand screed from the 6th to the 8th floor - 100%
Parking:
- Masonry of external and internal partition walls - 5%