Construction progress for December 2025
05.01.2026
Go back
In December 2025, the following works were carried out at the construction site:
Section 1:
- Facade installation - 25%
- Heating and water supply system installation on the 1st floor - 90%
- Installation of ventilation equipment (valves) - 60%
Section 2:
- Heating and water supply system installation on the 1st floor - 90%
- Facade installation - 18%
- Floor leveling in apartments and public areas on the 2nd and 3rd floors - 95%
- Installation of ventilation equipment (valves) - 60%
Section 3:
- Facade installation - 20%
- Installation of ventilation equipment (valves) - 60%
Section 4:
- Facade installation - 27%
- Installation of ventilation equipment (valves) - 60%
- Installation of elevator equipment - 80%
- Heating and water supply system installation on the 1st floor - 90%
- Floor leveling on the 1st floor - 90%
Section 5:
- Facade installation - 25%
- Heating and water supply system installation on the 1st floor - 90%
- Floor leveling on the 1st floor - 90%
- Installation of ventilation equipment (valves) - 60%
Parking:
- Masonry of walls and partitions - 19%