Construction progress for October 2025
05.11.2025
Go back
In October 2025, the following works were performed at the construction site:
Section 1:
- Facade installation – 17%
- Terrace installation on the 7th floor – 40%
- Plastering walls on the 3rd floor – 100%
Section 2:
- Roof installation – 90%
- Installation of engineering networks on floors 2 to 8 – 90%
- Facade installation – 13%
- Elevator equipment installation – 95%
Section 3:
- Drilling holes for Freon outlets for air conditioners – 85%
- Roof installation – 90%
- Facade installation – 17%
Section 4:
- Facade installation – 25%
- Cement-sand screed from floors 2 to 6 – 100%
- Roof boiler installation – 50%
- Roof installation – 90%
- Drilling holes for Freon outlets for air conditioners – 80%
Section 5:
- Drilling holes for Freon outlets for air conditioners – 90%
- Facade installation – 20%
- Elevator equipment installation – 80%
Parking:
- Masonry of external and internal walls and partitions – 15%