In October 2025, the following works were performed at the construction site:

Section 1:

  • Facade installation – 17%
  • Terrace installation on the 7th floor – 40%
  • Plastering walls on the 3rd floor – 100%

Section 2:

  • Roof installation – 90%
  • Installation of engineering networks on floors 2 to 8 – 90%
  • Facade installation – 13%
  • Elevator equipment installation – 95%

Section 3:

  • Drilling holes for Freon outlets for air conditioners – 85%
  • Roof installation – 90%
  • Facade installation – 17%

Section 4:

  • Facade installation – 25%
  • Cement-sand screed from floors 2 to 6 – 100%
  • Roof boiler installation – 50%
  • Roof installation – 90%
  • Drilling holes for Freon outlets for air conditioners – 80%

Section 5:

  • Drilling holes for Freon outlets for air conditioners – 90%
  • Facade installation – 20%
  • Elevator equipment installation – 80%

Parking:

  • Masonry of external and internal walls and partitions – 15%