OLEGIV Podil
Construction progress for September 2025

01.10.2025

Go back

In September 2025, the following works were carried out at the construction site:

Section 1:

  • Facade installation - 15%
  • Installation of electrical networks on the 3rd floor in MZK according to the design project - 100%
  • Installation of elevator equipment - 100%
  • Plastering of walls on the 3rd floor in MZK - 50%
  • Installation of windows on the staircases - 100%
  • Monolithic filling of openings in the floor slab after laying engineering networks - 75%
  • Drilling holes for freon piping for air conditioners - 75%

Section 2:

  • Soundproofing and floor installation in apartments, waterproofing in bathrooms, as well as preparation of balconies for cement-sand screed from the 2nd to the 8th floors - 100%
  • Installation of windows on the staircases - 100%
  • Roofing - 20%
  • Installation of heating risers in MZK - 100%
  • Facade installation - 10%
  • Installation of elevator equipment - 20%

Section 3:

  • Installation of windows on the staircase - 100%
  • Drilling holes for freon piping for air conditioners - 55%
  • Roofing - 20%
  • Facade installation - 15%

Section 4:

  • Facade installation - 10%
  • Installation of cement-sand screed on the 7-8 floors - 100%
  • Installation of engineering networks on floors 2 to 8 - 100%
  • Installation of windows on the staircases - 100%
  • Installation of heating risers in MZK - 100%
  • Roofing - 20%

Section 5:

  • Installation of windows on the staircases - 100%
  • Installation of heating risers in MZK - 100%
  • Drilling holes for freon piping for air conditioners - 40%
  • Installation of engineering networks on floors 2 to 8 - 100%
  • Facade installation - 10%
  • Installation of cement-sand screed from 2 to 5 floors - 100%

Parking:

  • Masonry of external and internal partition walls - 10%