Construction progress for September 2025
01.10.2025
Go back
In September 2025, the following works were carried out at the construction site:
Section 1:
- Facade installation - 15%
- Installation of electrical networks on the 3rd floor in MZK according to the design project - 100%
- Installation of elevator equipment - 100%
- Plastering of walls on the 3rd floor in MZK - 50%
- Installation of windows on the staircases - 100%
- Monolithic filling of openings in the floor slab after laying engineering networks - 75%
- Drilling holes for freon piping for air conditioners - 75%
Section 2:
- Soundproofing and floor installation in apartments, waterproofing in bathrooms, as well as preparation of balconies for cement-sand screed from the 2nd to the 8th floors - 100%
- Installation of windows on the staircases - 100%
- Roofing - 20%
- Installation of heating risers in MZK - 100%
- Facade installation - 10%
- Installation of elevator equipment - 20%
Section 3:
- Installation of windows on the staircase - 100%
- Drilling holes for freon piping for air conditioners - 55%
- Roofing - 20%
- Facade installation - 15%
Section 4:
- Facade installation - 10%
- Installation of cement-sand screed on the 7-8 floors - 100%
- Installation of engineering networks on floors 2 to 8 - 100%
- Installation of windows on the staircases - 100%
- Installation of heating risers in MZK - 100%
- Roofing - 20%
Section 5:
- Installation of windows on the staircases - 100%
- Installation of heating risers in MZK - 100%
- Drilling holes for freon piping for air conditioners - 40%
- Installation of engineering networks on floors 2 to 8 - 100%
- Facade installation - 10%
- Installation of cement-sand screed from 2 to 5 floors - 100%
Parking:
- Masonry of external and internal partition walls - 10%