Construction progress for November 2025

05.12.2025

Go back

In November 2025, the following works were completed on the construction site:

Section 1:

  • Facade installation - 20%
  • Roofing installation - 25% +29.450
  • Installation of ventilation equipment (valves) - 25%

Section 2:

  • Roofing installation - 80% at +29.450 and at +28.000
  • Installation of engineering networks in the screed - 20%
  • Facade installation - 15%
  • Installation of K1 standpipes - 100%
  • Screed installation in apartments and common areas from the 4th to the 8th floors - 90%

Section 3:

  • Elevator equipment installation - 85%
  • Roofing installation in the R-P/8-11 scope at +26.600 - 100% and at +29.450 and +28.000 - 80%
  • Facade installation - 19%
  • Exterior lighting installation on the facade - 20%

Section 4:

  • Facade installation - 25%
  • Roofing installation - 80% at +29.450 and at +28.000
  • Installation of K1 standpipes - 100%
  • Exterior lighting installation on the facade - 25%
  • Installation of brackets for air conditioner units - 80%

Section 5:

  • Facade installation - 22%
  • Roofing installation - 20% +29.450
  • Installation of K1 standpipes - 50%
  • Exterior lighting installation on the facade - 20%

Parking:

  • Masonry of walls and partitions - 17%