Construction progress for November 2025
05.12.2025
Go back
In November 2025, the following works were completed on the construction site:
Section 1:
- Facade installation - 20%
- Roofing installation - 25% +29.450
- Installation of ventilation equipment (valves) - 25%
Section 2:
- Roofing installation - 80% at +29.450 and at +28.000
- Installation of engineering networks in the screed - 20%
- Facade installation - 15%
- Installation of K1 standpipes - 100%
- Screed installation in apartments and common areas from the 4th to the 8th floors - 90%
Section 3:
- Elevator equipment installation - 85%
- Roofing installation in the R-P/8-11 scope at +26.600 - 100% and at +29.450 and +28.000 - 80%
- Facade installation - 19%
- Exterior lighting installation on the facade - 20%
Section 4:
- Facade installation - 25%
- Roofing installation - 80% at +29.450 and at +28.000
- Installation of K1 standpipes - 100%
- Exterior lighting installation on the facade - 25%
- Installation of brackets for air conditioner units - 80%
Section 5:
- Facade installation - 22%
- Roofing installation - 20% +29.450
- Installation of K1 standpipes - 50%
- Exterior lighting installation on the facade - 20%
Parking:
- Masonry of walls and partitions - 17%