OLEGIV Podil
Construction progress for January 2025

01.02.2025

Go back

In January 2025, the following work was completed on the construction site:

Section 1:

  • Window installation 1st and 2nd floor – 75%
  • Masonry of exterior and interior partition walls from 5th to 7th floor – 75%, 8th floor – 90%

Section 2:

  • Masonry of exterior and interior partition walls from 5th to 6th floor – 45%

Section 3:

  • Masonry of exterior and interior partition walls 5th floor – 85%, 6th floor – 80%, 7th-8th floor – 75%

Section 4:

  • Masonry of exterior and interior walls from 4th to 6th floor – 50%

Section 5:

  • Masonry of exterior and interior walls from 4th to 6th floor – 50%

Parking (1 zone):

  • Installation of the covering slab – 25%