Construction progress for May 2025
02.06.2025
Go back
In May 2025, the following works were performed at the construction site:
Section 1:
- Masonry of external and internal partition walls: 1st floor – 95%, 3rd floor – 95%, 4th floor – 70%, 5th floor – 95%
- Roofing installation – 75%
- Installation of internal plumbing and sewage systems – 55%
Section 2:
- Masonry of external and internal partition walls: 1st floor – 95%, 3rd floor – 95%, 4th floor – 55%, 8th floor – 55%
- Window installation: 1-4 floors – 80%
Section 3:
- Masonry of smoke shafts on the roof – 40%
- Installation of internal plumbing and sewage systems – 55%
- Installation of internal electrical and heating systems in apartments and common areas –- 5%
- Soundproofing of floors, preparation for cement screed – 5%
Section 4:
- Masonry of external and internal walls: 4-6 floors – 95%
- Window installation: 1st floor – 95%, 2-8 floors – 85%
Section 5:
- Masonry of external and internal walls: 3rd floor – 55%, 4th floor – 60%, 5-6 floors – 95%
- Roofing installation – 50%
- Installation of internal plumbing and sewage systems – 45%
Retaining wall:
- Installation of a retaining wall along axis 17 – 100%