Park Lake City
Construction progress for December 2022

27.12.2022

Go back

Park Lake City by DIM is under construction! Already built houses majestically and kindly greet their residents. Luxurious lobbies, service from the management company, unsurpassed landscaping and natural untouched beauty make life in Park Lake City unforgettable and romantic.

We share the latest news from the construction site, how quickly our exquisite homes are growing. We thank the investors who pay their installments on time. Thanks to you, we continue construction!

We invite you to view a photo report from the construction site for December:

VITA Quarter, first phase

Playground:

  • Applying the finishing coat – 95%

  • Lighting work is underway – 100%

  • Automatic watering device – 95%

  • Landscaping works – 100%

House No. 1:

  • Installation of benches – 100%

  • Installation of parking lot coverage – 5%

  • Landscaping works – 80%

House No. 2:

  • Re-equipment of the recreation area, barbecue – 50%

  • Installation of benches – 100%

House No. 3:

  • Automatic watering device – 99%

  • Installing a treadmill near the house – 95%

  • Tree planting – 95%

  • Connecting electric boilers to systems – 100%

  • Boiler dispatching – 75%

  • Installation of benches – 100%

  • Installation of convectors in technical rooms – 100%

  • Boiler supply – 100%

  • Installation of ventilation grilles on the roof – 100%

  • Backfilling of porches with pebbles – 10%

House No. 4:

  • Tiling of porches around the house – 100%

  • Automatic watering device – 99%

  • Preparation of vertical planning for tree planting – 100%

  • Connecting electric boilers to systems – 100%

  • Insulation of cold water risers – 100%

  • Installation of convectors in technical rooms – 100%

  • Boiler dispatching – 85%

  • Tree planting – 95%

  • Installation of ventilation grilles on the roof – 15%

House No. 5:

  • Brickwork is done throughout the house – 95%

  • Pulling of EO cables according to a permanent scheme – 80%

  • Roof installation – 93%

Clean water tank:

  • SS – 5%

  • Reservoir hilling, preparation of landscaping for final coating – 95%

  • Connection of EO under a permanent scheme – 100%

  • Beach area coverage – 70%

  • Installation of outdoor lighting poles – 100%

VITA Quarter, second phase

House No. 2.1:

  • Installation of mortgaged balcony railings – 100%

  • Work is underway to distribute electricity – 65%

  • Waterproofing of balconies – 100%

  • Facade installation – 75%

  • Screed work is being carried out on the balconies – 100%

  • Facade lighting work is underway – 70%

  • Installation of wiring for a video surveillance system – 90%

House No. 2.2:

  • Facade installation – 75%

  • Installation of mortgaged balcony railings – 100%

  • Waterproofing of balconies – 100%

  • Facade lighting work is underway – 30%

  • Installation of screed on balconies – 100%

  • Installation of wiring for a video surveillance system – 90%

  • Installation of drains on balconies – 40%

  • Installation of balcony railing posts – 25%

House No. 2.3:

  • Roofing work is underway – 65%

House No. 2.4:

  • Masonry work completed – 95%

  • Installation of window structures – 99%

House No. 2.5:

Masonry installation – 95%

AUQA Quarter 2

Parking:

Soil replacement – 80%

TERRA Quarter 1

House No. 1:

  • Soil replacement, backfilling of the pit and compaction of the base – 100%

House No. 2:

  • Masonry installation – 3%

  • Installation of an automatic watering chamber – 30%