Construction progress for September 2022
29.09.2022
Construction progress of the Park Lake City residential complex in September 2022
In September, the construction of the Park Lake City business-class club-style suburban complex, located near Kyiv, gained new momentum. Four buildings of this complex have already been put into operation.
In September 2022, the following work was performed at the Park Lake City residential complex construction site:
VITA Quarter, first phase
BUILDING No. 1.1:
restoration of green cover in front gardens after lifting automatic irrigation – 100%
BUILDING No. 1.2:
restoration of green cover in front gardens after lifting automatic irrigation – 100%
Re-equipment of the recreation area, fireplace – 30%
BUILDING No. 1.3:
finishing of brick partitions on the 1st floor between the verandas – 100%
completion of facade works (adjacency to porches) – 100%
front gardens, landscaping, grass carpet – 100%
landscaping, grass sowing – 100%
tree planting – 10%
insulation of cold water risers – 70%
connecting electric boilers to the system – 90%
BUILDING No. 1.4:
preparation of vertical planning for tree planting – 80%
connecting electric boilers to the system – 10%
radiator installation – 100%
tiling the porch around the house – 100%
insulation of cold water risers – 70%
BUILDING No. 1.5:
roof installation – 95%
CHILDREN'S PLAYGROUND
installation of equipment for young children – 100%
applying the finishing coat – 60%
CLEAN WATER TANK
connection of EO under a permanent scheme – 95%
VITA Quarter, second phase
BUILDING No. 2.1:
facade decoration – 75%
electricity distribution device – 50%
installation of mortgages for balcony railings – 100%
waterproofing of balconies – 50%
BUILDING No. 2.2:
facade decoration – 75%
waterproofing of balconies – 100%
BUILDING No. 2.4:
installation of window structures – 99%
masonry installation – 95%
BUILDING No. 2.5:
bricklaying – 35%
AQUA Quarter
PARKING
soil replacement – 100%
Terra Quarter
HOUSE NO. 1:
soil replacement, backfilling of the pit and compaction of the base – 100%