Construction progress for October 2022
10.10.2022
Despite the difficulties in organizing the construction process and constant power outages, our favorite PARK LAKE CITY is being built on schedule.
Thank you for the timely payment of installments, thanks to which we maintain a high pace of construction.
Let us remind you that buildings 1.3 and 1.4 of the second stage have already been put into operation and the process of handing over the keys to new residents is currently underway.
We share the October report on the construction of the best suburban complex PARK LAKE CITY:
VITA Quarter, first phase
CHILDREN'S PLAYGROUND:
application of the finishing coating – 95%;
lighting performance – 100%;
automatic watering device – 95%;
landscaping work – 95%.
HOUSE NO. 1:
installation of benches – 100% - Covered parking – 5%;
landscaping work – 25%.
HOUSE NO. 2:
Re-equipment of the recreation area, fireplace – 50%
installation of benches – 100%
HOUSE #3:
automatic watering device – 99%;
installing a treadmill near the house – 95%;
tree planting – 95%;
connection of electric boilers to systems – 100%;
boiler dispatching – 25%;
installation of benches – 100%;
installation of convectors in technical rooms – 100%;
boiler supply – 100%.
HOUSE NO. 4:
tiling of porches around the house – 100%;
automatic watering device – 50%;
preparation of vertical planning for tree planting – 80%;
connection of electric boilers to systems – 10%;
insulation of cold water risers – 70%.
HOUSE NO. 5:
brickwork of the entire house – 95%;
pulling of EO cables according to a permanent scheme – 80%;
roof installation – 5%.
CLEAN WATER TANK:
SS – 5%
tank hilling, preparation of landscaping for final coating – 95%;
connection of EO under a permanent scheme – 90%.
VITA Quarter, second phase
BUILDING No. 2.1:
installation of mortgaged balcony railings – 100%;
electricity distribution device – 50%;
waterproofing of balconies – 50%;
facade arrangement – 75%.
BUILDING No. 2.2:
facade arrangement – 75%;
installation of mortgaged balcony railings – 100%;
Waterproofing of balconies – 100%.
BUILDING No. 2.4:
masonry installation – 95% (the rest after the raised floor slab);
installation of window structures – 99%.
AQUA Quarter
PARKING:
soil replacement – 50%.
Terra Quarter
HOUSE NO. 1:
soil replacement, backfilling of the pit and compaction of the base – 100%.