Park Lake City
Construction progress for November 2022

30.11.2022

Go back

Construction progress of the Park Lake City residential complex in November 2022

Sophisticated, technological, unique, and many, many more compliments can be given to Park Lake City by DIM. The project itself, its surroundings, and the atmosphere speak of love, peace, happiness, and the zen that everyone who comes to their home or to visit feels.

Meanwhile, our dedicated builders do their job with love and enthusiasm - continuing to create the most beautiful homes in Park Lake City.

We invite you to view a fresh photo report from the construction site for November:

VITA Quarter, first phase

Playground:

  • Applying the finishing coat

  • Lighting work is underway.

  • Automatic watering device

  • Landscaping works

House No. 1:

  • Installing benches

  • Installation of parking lot covering

  • Landscaping works

House No. 2:

  • Refurbishment of the recreation area, barbecue

  • Installing benches

House No. 3:

  • Automatic watering device

  • Installing a treadmill near the house

  • Planting trees

  • Connecting electric boilers to systems

  • Boiler dispatching

  • Installing benches

  • Installation of convectors in technical rooms

  • Supply of boilers

  • Installation of ventilation grilles on the roof

House No. 4:

  • Tiling porches around the house

  • Automatic watering device

  • Preparing vertical layout for tree planting

  • Connecting electric boilers to systems

  • Insulation of cold water risers

  • Installation of convectors in technical rooms

  • Boiler dispatching

  • Planting trees

  • Installation of ventilation grilles on the roof

House No. 5:

  • Brickwork is done throughout the house

  • Pulling EO cables according to a permanent scheme

  • Roof installation

Clean water tank:

  • SS

  • Hilling the reservoir, preparing the landscaping for the final coating

  • Connecting the EO according to a permanent scheme

  • Beach area cladding

VITA quarter, second line

House No. 2.1:

  • Installation of mortgages for balcony railings

  • Electricity distribution work is underway.

  • Waterproofing of balconies

  • Facade arrangement

  • Screed work is being carried out on the balconies

  • Facade lighting work is underway.

  • Installation of wiring for a video surveillance system

House No. 2.2:

  • Facade arrangement

  • Installation of mortgages for balcony railings

  • Waterproofing of balconies

  • Facade lighting work is underway.

  • Installing screed on balconies

  • Installation of wiring for a video surveillance system

House No. 2.3:

  • Roofing work is underway.

House No. 2.4:

  • Execution of masonry work (remaining after the raised floor slab)

  • Installation of window structures

House No. 2.5:

  • Masonry arrangement

AUQA Quarter 2

Parking:

  • Soil replacement

TERRA Quarter 1

House No. 1:

  • Soil replacement, backfilling of the excavation and compaction of the base

House No. 2:

  • Masonry arrangement