Construction progress for January 2022
10.01.2022
Construction progress of the Park Lake City residential complex in January 2022
A suburban residential complex located 20 minutes by car from the center of the capital. Low-rise buildings, spacious territory and its own pond in the center. The first two houses have already been put into operation.
In January 2022, the following work is being carried out at the Park Lake City residential complex construction site:
VITA Quarter, first phase
House No. 1.1, 1.2:
elimination of comments from the operation service.
House No. 1.3:
installation of electrical fittings.
installation of plumbing fittings.
installation of SKD fittings.
painting work is being carried out.
Decoration work is being carried out.
lightning protection installation.
The territory is being improved.
House No. 1.4:
installation of electrical fittings.
installation of plumbing fittings.
installation of SKD fittings.
painting work is being carried out.
Decorative work is being carried out.
lightning protection installation.
The territory is being improved.
House No. 1.5:
installation of monolithic stairs and parapet.
brickwork installation 2 floors.
VITA Quarter, second phase
House No. 2.1:
installation of brickwork on the roof.
facade arrangement.
installation of PVC structures.
roof installation.
House No. 2.2:
facade arrangement.
installation of PVC structures.
installation of brickwork on the roof.
roof installation. ⠀
House No. 2.3:
brickwork arrangement 1 - 4 floors.
House No. 2.4:
installation of brickwork on the 1st floor and roof.
House No. 2.5:
arrangement of staircases.
installation of ventilation units.
House No. 2.6:
foundation slab structure.
installation of vertical formwork for the 1st floor.
AQUA Quarter
House No. 1:
parapet installation.
House No. 3:
backfilling of the excavation.
Terra Quarter
House No. 2:
backfilling of foundations.
reinforcement of vertical elements of the 1st floor.
installation of the K1 system.
House No. 3:
backfilling of foundations.
reinforcement of vertical elements of the 1st floor.
installation of the K1 system.