Construction progress for April 2023
20.04.2023
We are providing a fresh report on the construction of PARK LAKE CITY for April. We continue to build relentlessly and increase the pace of construction.
VITA Quarter, first phase
Improvement:
Work is underway to improve the territory, plant greenery, and plant trees:
Marking has been made for planting perennials in the zone 1-2-3-4 of houses
Perennials are being planted in the beach area
Beach arrangement – 100%
House No. 1.5:
Roof installation – 100%
Installation of covers on ventilation ducts – 100%
Installation of freon pipes – 100%
Installation of the K14 system - 95%
Basement waterproofing – 50%
Preparatory work for the installation of elevators is being carried out – 3%
Installation of fan pipes – 100%
VITA quarter, second line
House No. 2.1:
Installation of covers on ventilation ducts – 100%
Installation of ventilation grilles on the roof – 5%
Installation of fan pipes – 100%
Installation of internal partitions – 85%
House No. 2.2:
Installation of covers on ventilation ducts – 100%
Installation of fan pipes – 100%
House No. 2.3:
Basement waterproofing – 100%
Soil replacement – 40%
Installation of fan pipes – 100%
House No. 2.4
Installation of freon pipes – 35%
Installation of the K14 system - 95%
Basement waterproofing – 65%
House No. 2.6:
Monolith installation – 8%