Construction progress for April 2023

20.04.2023

Go back

We are providing a fresh report on the construction of PARK LAKE CITY for April. We continue to build relentlessly and increase the pace of construction.

VITA Quarter, first phase

Improvement:

Work is underway to improve the territory, plant greenery, and plant trees:

  • Marking has been made for planting perennials in the zone 1-2-3-4 of houses

  • Perennials are being planted in the beach area

  • Beach arrangement – 100%

House No. 1.5:

  • Roof installation – 100%

  • Installation of covers on ventilation ducts – 100%

  • Installation of freon pipes – 100%

  • Installation of the K14 system - 95%

  • Basement waterproofing – 50%

  • Preparatory work for the installation of elevators is being carried out – 3%

  • Installation of fan pipes – 100%

VITA quarter, second line

House No. 2.1:

  • Installation of covers on ventilation ducts – 100%

  • Installation of ventilation grilles on the roof – 5%

  • Installation of fan pipes – 100%

  • Installation of internal partitions – 85%

House No. 2.2:

  • Installation of covers on ventilation ducts – 100%

  • Installation of fan pipes – 100%

House No. 2.3:

  • Basement waterproofing – 100%

  • Soil replacement – 40%

  • Installation of fan pipes – 100%

House No. 2.4

  • Installation of freon pipes – 35%

  • Installation of the K14 system - 95%

  • Basement waterproofing – 65%

House No. 2.6:

  • Monolith installation – 8%