Construction progress for October 2023
17.10.2023
Park Lake City by DIM is actively under construction.
We share the latest construction report for October:
VITA Quarter, first phase
House No. 1.5:
Arrangement of sand filling of the first floor for the load-bearing floor – 100%
Insulation for the power floor – 100%
Power floor installation – 100%
VITA quarter, second line
House No. 2.1:
Facade arrangement – 92%
Installation of porcelain tiles on the facade – 86%
Installation of SPOK aluminum – 90%
Installation of plaster MOS – 90%
Heating wiring – 80%
Installation of SKD – 65%
Installation of tiles on balconies – 80%
Screed installation – 25%
Installation K1, K2, B1 – 20%
Installation of external networks – 10%
Improvement – 20%
House No. 2.2:
Arrangement of front gardens – 100%
House No. 2.4:
Facade installation – 31%
Roof installation – 50%
Installation of SPOK aluminum – 80%
House No. 2.7:
Soil replacement for the building foundation – 100%
Installation of geothermal wells for heat pumps – 3%
AQUA Quarter, first phase
House No. 1.1:
Brickwork installation – 75%
House No. 1.3:
Installation of a monolithic building frame – 100%