Construction progress for October 2023

17.10.2023

Go back

Park Lake City by DIM is actively under construction.

We share the latest construction report for October:

VITA Quarter, first phase

House No. 1.5:

  • Arrangement of sand filling of the first floor for the load-bearing floor – 100%

  • Insulation for the power floor – 100%

  • Power floor installation – 100%

VITA quarter, second line

House No. 2.1:

  • Facade arrangement – 92%

  • Installation of porcelain tiles on the facade – 86%

  • Installation of SPOK aluminum – 90%

  • Installation of plaster MOS – 90%

  • Heating wiring – 80%

  • Installation of SKD – 65%

  • Installation of tiles on balconies – 80%

  • Screed installation – 25%

  • Installation K1, K2, B1 – 20%

  • Installation of external networks – 10%

  • Improvement – 20%

House No. 2.2:

  • Arrangement of front gardens – 100%

House No. 2.4:

  • Facade installation – 31%

  • Roof installation – 50%

  • Installation of SPOK aluminum – 80%

House No. 2.7:

  • Soil replacement for the building foundation – 100%

  • Installation of geothermal wells for heat pumps – 3%

AQUA Quarter, first phase

House No. 1.1:

  • Brickwork installation – 75%

House No. 1.3:

  • Installation of a monolithic building frame – 100%